DCPL-K4A02<br />

On completion, the work will be finally checked and approved by the<br />

Engineer. In case where excavation in soil, soft and decomposed rock<br />

and/or hard rock are involved, the soil or soft and decomposed rock layers,<br />

shall be removed by turn and levels of the underlying rock surfaces observed<br />

to enable measurements. Further work shall be resumed after getting<br />

clearance from the Engineer.<br />

3.6.3 Excavation in Hard Rock<br />

3.6.4 Blasting<br />

3.6.4.1 General<br />

Overburden, if any, consisting of top soil, ordinary and hard soil, soft<br />

and decomposed rock as per classification of soil, which do not require<br />

blasting shall be completely stripped off and the levels of the hard rock<br />

surface shall be taken to enable measurement. Further work in hard rock<br />

shall be resumed after clearance from the Engineer.<br />

Personnel deployed for rock excavations shall be protected from all<br />

hazards such as loose rock/boulder rolling down and from general slips of<br />

excavated surfaces. Where the excavated surface is such that it is not<br />

stable against sliding, necessary supports, props, bracings or bulkheads<br />

shall be provided and maintained during the period of construction. Where<br />

danger exists of loose rock/boulder falling from the excavated surfaces<br />

deeper than 2 metres, steel mesh anchored to the lower edge of<br />

excavation and extending over and above the rock face, adequate to<br />

retain the dislodged material shall be provided and maintained.<br />

In case where blasting, though otherwise required, is prohibited for any<br />

reasons, the excavation shall be carried out by chiselling, wedging or<br />

any other approved method. All loose or loosened rock in the sides shall be<br />

removed by barring, wedging, etc.<br />

Excavation shall be continued in hard rock to such widths, lengths,<br />

depths and profiles as are shown on the drawings or such other lines and<br />

grades as may be specified by the Engineer. As far as possible all blasting<br />

shall be completed prior to commencement of construction. At all stages of<br />

excavation, precautions shall be taken to preserve the rock below and<br />

beyond the lines for the excavation, in the soundest possible condition.<br />

The quantity and strength of explosive used, shall be such as will neither<br />

damage nor crack the rock outside the limits of excavation. All<br />

precautions, as directed by Engineer, shall be taken during the blasting<br />

operations and care shall be taken that no damage is caused to adjoining<br />

buildings or structure as a result of blasting operations. In case of damage<br />

to permanent or temporary structures, Contractor shall repair the same<br />

to the satisfaction of Engineer. As excavation approaches its final lines and<br />

levels, the depth of the charge holes and amount of explosives used shall be<br />

progressively and suitably reduced.<br />

Unless otherwise stated herein, I.S. Specification IS:4081 "Safety Code for<br />

Blasting & Related Drilling Operation" shall be followed.<br />

(PCA.774.S034sca) V.II-D2/S-I : 8