TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 16 OF 35<br />

18.0 PROJECT MANAGEMENT/ CONSTRUCTION MANAGEMENT<br />

To meet the need of construction management at site, contractor shall provide the<br />

following services within quoted/ accepted rates.<br />

18.1 PLANNING & MONITORING<br />

18.1.1 The bidder shall prepare detail construction schedule (L-3) as per completion dates<br />

given in this document. This schedule must include all milestone and key activities<br />

for each subsystems/ components in the areas of engineering (wherever<br />

applicable), procurement, manufacture (wherever applicable), despatch,<br />

excavation/ construction/ erection. This network must conform to the overall project<br />

schedule. The bidder should also ensure monitoring of these activities at least<br />

weekly basis to start with and on daily basis whenever required by BHEL.<br />

Sl<br />

Work to be completed Period from<br />

no<br />

start of work<br />

1 Completion of excavation, PCC Within 70 days<br />

2 Completion of chimney raft casting & order placing for stack Within 135<br />

elevator.<br />

days<br />

3 Completion of Inter form equipment erection (1st stage). Within 160<br />

days<br />

4 Completion of RCC shell concreting upto EL (+) 5 M. Within 190<br />

days<br />

5 Completion of electrical winch, passenger hoist external &<br />

internal platform etc fixing (2nd & final stage of Interform<br />

equipment erection), temporary lightening arrestor with<br />

electrode, temporary aviation obstruction lighting system,<br />

temporary communication system.<br />

6 Completion of slip form concreting, dismantling of slip form<br />

equipment (part), roof casting.<br />

7 Completion of mini shell concreting & slip form equipment<br />

dismantling (balance portion).<br />

8 Completion of all corbel, internal painting, brick flue lining,<br />

insulation, MS liner bands fixing, completion of permanent<br />

earthing system and hopper including AR bricks completion,<br />

and readiness for boiler light up.<br />

9 Completion of erection of external platform, ladder, all<br />

electrical installation. All MS doors & access doors and<br />

sampling pot erection completion, rain water pipe fixing and<br />

mini shell cap fixing, erection completion of stack elevator<br />

with commissioning.<br />

Within 220<br />

days<br />

Within 430<br />

days<br />

Within 480<br />

days<br />

Within 800<br />

days<br />

Within 930<br />

days<br />

10 Completion of external painting and all other finishing work Within 990<br />

and completion of all chimney works in all respects. days<br />

18.1.2 The bidder shall also prepare progress report indicating progress on key activities,<br />

management summary for critical activities, list of actions requiring attention of<br />

BHEL. This schedule is to be preferably made in MS PROJECTS, so that the same<br />

is compatible with BHEL’s project management software.<br />

18.1.3 The bidder will have to install one no PCs with the minimum specification of<br />

(multimedia PC work station Pentium-Duo, 1 GHZ or above, 120 GB HDD, 1GB<br />

RAM, 100 MBPS LAN card of HCL/ COMPAQ/ ZENITH or equivalent make with<br />

window XP (professional) O/S and required software like MS Office 2007<br />

Professional, AutoCAD 2007, PageMaker (7.0 etc), ADOBE PDF CREATOR with<br />

one no laser jet printer compatible for A3 size printing (cartridge to be supplied as 1<br />

cartridge per 4 months or depending on the requirement, whichever is less), one<br />

nos. laser jet printer compatible for A4 size printing ((cartridge to be supplied as 1<br />

cartridge per 4 months or depending on the requirement, whichever is less) with<br />

power backup at places, as per instruction of BHEL for exclusive use of BHEL.<br />

These computers, printers shall remain contractor’s property and they will be<br />

allowed to take out the same after completion of the site works. The contractor shall