TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 28 OF 35<br />

same shall be provided by contractor at his own cost.<br />

28.2 Customer/ BHEL will provide space for fabrication yard within plant premises.<br />

However; during execution, based on actual site conditions, requirement and layout<br />

and approaches, the above may change suitably.<br />

29.0 CIVIL LABORATORY AT SITE<br />

29.1 Contractor shall establish and maintain civil laboratory at site with equipments as<br />

listed in Annexure `A`<br />

29.1.1 Setting time of cement, compressive strength of cement, concrete cubes, bricks<br />

etc.<br />

29.1.2 Water absorption test of bricks.<br />

29.1.3 Earth compaction test (proctor density/ dry density and optimum moisture content,<br />

etc).<br />

29.1.4 Conducting of test for setting time and compressive strength of cement.<br />

29.1.5 Sieve analysis of fine aggregates and coarse aggregates.<br />

29.1.6 Bulking test of fine aggregates.<br />

29.1.7 Sieve analysis, moisture content, specific gravity and crushing strength of course<br />

aggregates<br />

29.1.8 Rapid moisture meter<br />

29.2 Other than above mentioned test, any testing required to be carried out at site as<br />

per Quality Plan and technical specification have to be arranged by contractor for<br />

all the works at his own cost.<br />

30.0 CONSTRUCTION SCHEDULE<br />

30.1 Entire work shall be carried out in accordance with the construction schedule within<br />

the stipulated completion period. Within 30 days of LOI, the contractor shall discuss<br />

with BHEL site engineer & furnish the (L-3) construction schedule based on<br />

milestones as per clause 14.1.1 for approval.<br />

30.2 Contractor will establish mix design within 40 days from the date of LOI.<br />

31.0 COMPLETION PERIOD<br />

The entire work under this scope shall be successfully completed in all respect<br />

within 33 months from the date of start of work as certified by BHEL engineer at<br />

site.<br />

The contractor shall mobilize at site and start the work within 30 days from date of<br />

written clearance by Construction Manager, BHEL, customer site.<br />

32.0 LIQUIDATED DAMAGE<br />

As per the provision of GCC.<br />

33.0 CERT<strong>IF</strong>ICATE TOWARDS COMPLETION<br />

The work under the scope of the contractor shall be deemed to have been<br />

completed in all respects only when so certified by BHEL. The decision of BHEL in<br />

this regard shall be final and binding on the contractor.<br />

34.0 GUARANTEE<br />

34.1 Even though the work will be carried out under supervision of BHEL, the contractor<br />

will be responsible for the quality of workmanship, quality of materials/ items and<br />

design for which the contractor is responsible.<br />

34.2 The contractor shall guarantee the work executed under the scope of the contract<br />

for a period of 12 (twelve) months from the date of start of guarantee period as<br />

certified by the Engineer (ie on completion of total work under scope and/ or taking<br />

over by BHEL) and shall rectify free of cost all defects due to faulty supply or work<br />

done. In case the contractor fails to repair/ replace the defective works within the<br />

time specified by the Engineer, BHEL may proceed to undertake the repairs/<br />

replace such defective works at contractor’s risk and cost without prejudice to any<br />

other rights and recover the same from security deposit/ other dues.<br />

35.0 INTEREST BEARING RECOVERABLE ADVANCE<br />

Not applicable for this tender.<br />

36.0 OVER RUN CHARGES<br />

No over run charges shall be paid to the contractor in the event the completion