DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-III<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

CEMENT CONCRETE (PLAIN & REINFORCED)<br />

1.0 SCOPE<br />

1.1 General<br />

This specification covers all the requirements, described hereinafter for<br />

general use of Plain and Reinforced Cement Concrete work in Structures<br />

and locations, cast-in-situ or precast, and shall include all incidental items of<br />

work not shown or specified but reasonably implied or necessary for the<br />

completion of the work.<br />

1.2 This specification shall also apply to the extent it has been referred to or<br />

applicable with the special requirements of structures covered in SCOPE of<br />

IS:456.<br />

1.3 IS:456 shall form a part of this specification and shall be complied with<br />

unless permitted otherwise. For any particular aspect not covered by this<br />

Code, appropriate IS Code, specifications and/or replacement by any<br />

International Code of practice as may be specified by the Engineer shall<br />

be followed. All codes and Standards shall conform to its latest revisions. A<br />

list of IS codes and Standards is enclosed hereinafter for reference.<br />

2.0 GENERAL<br />

2.1 Work to be provided for by the Contractor<br />

The work to be provided for by the Contractor, unless<br />

specified shall include but not be limited to the following :-<br />

otherwise<br />

a) Furnish all labour, supervision, services including facilities as may<br />

be required under statutory labour regulations, materials, forms,<br />

templates, supports, scaffolds, approaches, aids, construction<br />

equipment, tools and plants, transportations, etc. required for the<br />

work.<br />

b) Except where it is excluded from the Scope of Contract, Contractor<br />

shall prepare progressively and submit for approval detailed<br />

drawings and Bar Bending Schedules for reinforcement bars showing<br />

the positions and details of spacers, supports, chairs, hangers etc.<br />

c) Design and prepare working drawings of formworks, scaffolds,<br />

supports, etc. and submit for approval.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 1