DCPL-K4A02<br />

Slabs, beams and similar members shall be poured in one operation, unless<br />

otherwise instructed by the Engineer. Moulding, throating, drip course, etc.,<br />

shall be poured as shown on the drawings or as directed by the Engineer.<br />

Holes shall be provided and bolts, sleeves, anchors, fastenings or other<br />

fixtures shall be embedded in concrete as shown on the drawings or as<br />

directed by the Engineer. Any deviation therefrom shall be set right by the<br />

Contractor as instructed by the Engineer.<br />

In case the forms or supports get displaced during or immediately after<br />

the placement and bring the concrete surface out of alignment beyond<br />

tolerance limits, the Engineer may direct to remove the portion and<br />

reconstruct or repair the same.<br />

The Engineer shall decide upon the time interval between two placements of<br />

concrete of different ages coming in contact with each other, taking in<br />

consideration the degree of maturity of the older concrete, shrinkage,<br />

heat dissipation and the ability of the older concrete to withstand the load<br />

imposed upon it by the fresh placement.<br />

Once the concrete is deposited, consolidated and finished in its final<br />

position, it shall not be distributed.<br />

3.13 Construction Joints and Cold Joints<br />

3.13.1 Construction Joints<br />

It is always desirable to complete any concrete structure by continuous<br />

pouring in one operation. However, due to practical limitation of methods<br />

and equipment and certain design considerations, construction joints<br />

are formed by discontinuing concrete at certain predetermined stages. These<br />

joints will be formed in a manner specified in the drawings/ Instruction.<br />

Vertical construction joints will be made with rigid stop-board forms having<br />

slots for allowing passage of reinforcement rods and any other<br />

embedments and fixtures that may be shown. Next stage concrete shall be<br />

placed against construction joint as per clause 3.12. For water retaining<br />

structures and leak-proof buildings suitable approved water bars will be<br />

installed at the construction joints.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 21