3.8 Workability<br />

DCPL-K4A02<br />

Whenever the water-cement ratio dictated by durability consideration is<br />

lower than that required from strength criterion, the former shall be<br />

adopted.<br />

In general the water cement ratio between 0.4 and 0.45 will be desirable to<br />

satisfy the durability requirement and from the consideration of<br />

impermeability of conrete. The contractor may propose lower water<br />

cement ratio as mentioned above by addition of a suitable plasticizer /<br />

super-plasticizer. However the contractor has to propose specifically<br />

along with field trials in the event of lower cement content if found suitable<br />

along with a plasticizer. It will be preferable to use Melamine based<br />

plasticizer.<br />

The degree of workability necessary to allow the concrete to be well<br />

consolidated and to be worked into the corners of formwork and around<br />

the reinforcement and embedments and to give the required surface finish<br />

shall depend on the type and nature of structure and shall be based on<br />

experience and tests. The usual limits of consistency for various types of<br />

structures are given below :<br />

TABLE - III<br />

LIMITS OF CONSISTENCY<br />

Degree of<br />

workability<br />

Slump in mm with<br />

Standard Cone as<br />

per IS:1199<br />

Min. Max.<br />

Use for which concrete<br />

is suitable.<br />

Very low 0 25 Large Mass concrete<br />

structure with heavy<br />

compaction equipment,<br />

roads and like.<br />

Low 25 50 Uncongested wide and<br />

shallow R.C.C. structures.<br />

Medium 50 100 Deep but wide R.C.C.<br />

structures with congestion<br />

or reinforcement and<br />

inserts.<br />

High 100 150 Very narrow and deep<br />

R.C.C. structures with<br />

congestion due to<br />

reinforcement and inserts.<br />

(NOTE : Notwithstanding anything mentioned above, the slump to<br />

be obtained for work in progress shall be as per direction of<br />

the Engineer)<br />

(PCA.774.S034sca2) V.II-D2/S-III : 16