DCPL-K4A02<br />

manner, the date on which concrete is placed in each part of the work and<br />

the date on which the formwork is removed therefrom and have this<br />

record checked and countersigned by the Engineer regularly.<br />

The Contractor shall be responsible for the safe removal of the formwork<br />

and any work showing signs of damage through premature removal of<br />

formwork or loading shall be rejected and entirely reconstructed by<br />

him. The Engineer may, however, instruct to postpone the removal of<br />

formwork if he considers it necessary.<br />

Forms for various types of structural components shall not be removed<br />

before the minimum periods specified herein and the removal after the<br />

minimum periods shall also be subject to the approval of the Engineer in<br />

each case.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 31