DCPL-K4A02<br />

3.0 EXECUTION<br />

3.1.0 Shoulder Construction<br />

3.1.1 Description<br />

3.1.2 Materials<br />

This work shall consist of constructing shoulders on either side of the<br />

pavement, in accordance with the requirements of this specification and in<br />

conformity with the lines, grades and cross-sections shown on the drawings<br />

or as directed by the Engineer.<br />

Shoulder may be of selected earth or grannlar material conforming to the<br />

requirements of embankment construction or granular sub-base construction<br />

respectively.<br />

3.1.3 Construction Operations<br />

3.2.0 Kerb<br />

3.2.1 Material<br />

Except in the case of bituminous constructions, shoulders shall be<br />

constructed in advance of the laying of pavement courses. The compacted<br />

thickness of each layer of shoulder shall correspond to the compacted layer<br />

of pavement course to be laid adjacent to it. After compaction, the inside<br />

edges of shoulders shall be trimmed vertical and included area cleaned of all<br />

spilled material before proceeding with the construction of the pavement<br />

layer.<br />

In the case of bituminous courses, shouldering operations shall start only<br />

after the pavement course has been laid and compacted.<br />

Regardless of the method of laying, all shoulder construction material<br />

shall be placed directly on the shoulder. Any spilled material dragged on to<br />

the pavement surface shall be immediately removed, without damage to the<br />

pavement and the area so affected thoroughly cleaned.<br />

During all stages of shoulder construction, the required cross-fall shall be<br />

maintained to drain off surface water.<br />

Kerb, if required for construction of footpath, shall consist of precast<br />

concrete blocks with a concrete grade of M-15. The blocks shall be 100 mm<br />

wide and of suitable length. The depth of blocks unless otherwise mentioned<br />

elsewhere, shall be 375 mm considering 225 mm height of footpath from the<br />

road level.<br />

3.2.2 Laying<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 6