DCPL-K4A02<br />

detailed programme of work as proposed to be executed giving<br />

completion dates of excavation of the various areas and the time<br />

required for area-filling and compaction. The programme should also<br />

show how the excavation and area- filling quantities will be<br />

balanced, minimising temporary stacking of spoils. It is to be noted<br />

that the Engineer even after initial approval of the programme, may<br />

instruct to enhance or retard the progress of work during the actual<br />

execution, in order to match with overall construction schedule<br />

without attracting any claims from the Contractor. The initial<br />

programme being submitted by the Contractor should have<br />

sufficient flexibility to take care of such reasonable variations.<br />

b) Within 15 days of award, the Contractor shall submit drawings<br />

showing details of slopes, approaches, sump pits, dewatering lines,<br />

borrow pits, if any, fencing etc. for approval of the Engineer for<br />

adoption.<br />

(PCA.774.S034sca) V.II-D2/S-I : 20