DCPL-K4A02<br />

The degree of compaction shall be sufficient to achieve a dry density of not<br />

less than 90% of proctor's dry density at optimum moisture content as<br />

per IS-2720 (Part - VII) or a relative density of 75% as per IS-2720<br />

(Part-XIV) as applicable depending on the nature of back filling material as<br />

stated in clause no. 3.7.2 of this specification. The work of back-filling will<br />

be accepted after the Engineer is satisfied with the degree of compaction<br />

achieved.<br />

5.0.0 INFORMATION TO BE SUBMITTED<br />

5.1.0 With Tender<br />

5.2.0 After Award<br />

Details of Equipment proposed to be used for excavation, back-filling and<br />

compaction have to be submitted along with the tender.<br />

After award of the Contract the successful tenderer shall submit the<br />

following for approval and adoption :<br />

a) The Contractor shall submit a detailed programme of the work<br />

as proposed to be executed giving completion dates of<br />

excavation of the various foundations and the time required for<br />

back-filling and compaction after completing the foundation for<br />

structures.<br />

The programme should show how the excavation and back-filling<br />

quantities will be balanced, minimising temporary stacking of spoils.<br />

It is to be noted that the Engineer even after initial approval of the<br />

programme, may instruct to enhance or retard the progress of<br />

work during the actual execution, in order to match with the<br />

progress of foundations without attracting any claims from the<br />

Contractor. The initial programme being submitted by the<br />

Contractor should have sufficient flexibility to take care of such<br />

reasonable variations.<br />

b) The Contractor shall submit drawings showing details of slopes,<br />

shorings, approaches, sump pits, dewatering lines, fencing etc. for<br />

approval of the Engineer for adoption.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 17