Central electricity authority Annual Report 2009-10<br />
(i) Suggestions for annual budgetary exercise<br />
relating to Customs & Central Excise Duty<br />
for 2009-10<br />
(ii) Service Tax on Wheeling/ Transmission of<br />
Power<br />
(iii) Levy of Service tax on electricity<br />
transmission & SLDC charges<br />
(iv) Implementing the Integrated Energy Policy<br />
(IEP) : Action Taken Report by Ministry of<br />
Power<br />
(v) Report of the Study Group for preparation<br />
of a Road Map for Rapid Economic<br />
Development of Uttar Pradesh<br />
(vi) Suggestions for annual budgetary exercise<br />
relating to Customs & Central Excise Duty<br />
for 2010-11<br />
(vii) Disciplines in domestic regulations at the<br />
WTO<br />
(viii) Exemption of excise duty on liquid fuels<br />
(Low Sulphur Heavy Stock, Naptha, Diesel<br />
& Furnace Oil) used for <strong>power</strong> generation<br />
(ix) Clarifications on the exemptions for Mega<br />
& Ultra Mega Power Projects<br />
9.4 Data Bank for Cost of Generation of<br />
Power<br />
The process of creating a data bank<br />
regarding rate of sale of <strong>power</strong> classified by type<br />
of generation for various Utilities/SEBs/Power<br />
Departments is under progress. With the creation<br />
of a large number of generating companies, the<br />
work of data collection, sifting and compilation<br />
has increased manifold. A statement indicating<br />
region-wise rate of sale of <strong>power</strong> for various<br />
Central, State & Private utilities in the country<br />
for the period the year 2008-09 is given at<br />
Annexure-9C.<br />
9.5 Progress in Bidding Process of Ultra<br />
Mega Power Projects (UMPPs)<br />
CEA has been regularly associated with<br />
the finalization of Request for Qualification<br />
(RfQ), Request for Proposal (RfP) and Power<br />
Purchase Agreement (PPA) for setting up of<br />
Ultra Mega Power Projects (UMPPs) in the<br />
country and in this regard, had represented<br />
in various committees. The successful<br />
bidders for four Ultra Mega Power Projects<br />
have already been selected through the tariff<br />
based International Competitive Bidding<br />
process, based on the Capacity and Super/<br />
Critical technology, specified in the RfQ &<br />
RfP documents issued by the shell companies<br />
and Letter of Intent has been issued to the<br />
successful developers. The bidders quoted the<br />
tariff for 25 years. Power Finance Corporation<br />
is the designated Nodal Agency for the entire<br />
bid process. The status of various UMPPs is<br />
as under:<br />
i. Mundra UMPP (5x800 MW) in Gujarat<br />
The Letter of Intent (LoI) was awarded<br />
to M/s Tata Power Ltd. on 28 th December, 2006<br />
with a levelised tariff of Rs. 2.264 per Kwh. The<br />
project was handed over on 23.04.07.<br />
ii.<br />
Sasan UMPP (6x660 MW) in Madhya<br />
Pradesh<br />
The Letter of Intent (LoI) was awarded<br />
to M/s Reliance Power Ltd. on 1 st August, 2007<br />
with a levelised tariff of Rs. 1.196 per Kwh. The<br />
project was handed over on 07.08.07.<br />
iii. Krishnapatnam UMPP (5x800 MW) in<br />
Andhra Pradesh<br />
The Letter of Intent (LoI) was awarded to<br />
M/s Reliance Power Ltd. on 30 th November, 2007<br />
with a levelised tariff of Rs. 2.333 per Kwh. The<br />
project was handed over on 29.01.08.<br />
“CEA-Helping the Transformation of Indian Power Sector”<br />
99