Central electricity authority Annual Report 2009-10<br />
(2/2)<br />
S.No Name of UMPP Capacity<br />
(MW)<br />
Status<br />
3. Krinshnapatnam UMPP 6x660 (i) Krishnapatnam UMPP was transferred to the selected developer namely Reliance Power<br />
Ltd. in Jan. 2008.<br />
(ii)<br />
(iii)<br />
(iv)<br />
(v)<br />
(vi)<br />
Financial closure for the project is yet to be achieved.<br />
about 2422 acres (92%) has already been acquired and transferred to the developer. Transfer<br />
of balance land is under process by the state Government.<br />
The project was awarded with unit configuration of 5x800 MW. The developer had<br />
requested for flexibility in project configuration in respect to unit size. Procurers have<br />
given their consent for the flexibility in unit size. As per latest status, the developer has<br />
placed order for 6x660 MW units. The developer has filed petition & supplementary PPA<br />
before CERC on 13.04.10 for their clearance in regard to change in unit configuration.<br />
Approval of CERC is awaited.<br />
Preliminary works like boundary wall fencing, site grading, construction <strong>power</strong> supply,<br />
site office, stores etc. have been taken up by the developers at site. Area grading in Main<br />
Plant area has been completed.<br />
As per the original PPA, the first unit is schedule for commissioning in Sept,2013 and<br />
last unit in Oct,2015.<br />
4. Tilaiya UMPP 6x660 (i) The project has been awarded to M/s Reliance Power Limited on 12.2.09.<br />
(ii) The SPV had been transferred on 7.8.09 to the developer.<br />
(iii) Financial closure for the project is yet to be achieved<br />
(iv) Advance possession of 470 acres of private land taken.<br />
(v) First stage forest clearance for Main Plant area has been received on 3.2.10 .Process for<br />
(vi) final clearance for <strong>power</strong> plant land under progress.<br />
As per the original PPA, the first unit is schedule for commissioning in May,2013 and<br />
last unit in June,2017<br />