27.07.2014 Views

thermal power development - Infraline

thermal power development - Infraline

thermal power development - Infraline

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Central electricity authority Annual Report 2009-10<br />

From the Chairperson<br />

The Power Sector in India registered a growth of 6.6% in 2009-10 against the<br />

previous year growth of 2.74% with gross <strong>power</strong> generation by various utilities<br />

being 771 Billion kWh as against the previous year <strong>power</strong> generation of<br />

724 Billion kWh. The growth would have been higher but for less <strong>power</strong> generation<br />

by hydro <strong>power</strong> stations.<br />

The definition of commissioning of generating units has been revised by CEA and<br />

now a unit is declared commissioned only after it has attained full load on the<br />

designated fuel. During the year, a total of 9,585 MW generation capacity was<br />

added which comprised 9,546 MW Thermal (including 440 MW of Nuclear) and<br />

39 MW Hydro, thus raising the Installed Capacity of the country to 1,59,398 MW.<br />

CEA closely monitors the progress of various constructional activities of <strong>thermal</strong><br />

<strong>power</strong> projects under execution in the country. Project monitoring related activities<br />

emerge from Section 73 (f) functions and duties of authority of Electricity Act, 2003 which inter-alia envisages<br />

“To Promote and Assist in Timely Completion of Various Schemes and Project.” Visits are made by CEA<br />

officers to the project sites for assessing the progress of various construction activities and rendering necessary<br />

advice/assistance in resolving the problems being faced by the project authorities to meet the schedule of<br />

commissioning. The Construction Monitoring groups of CEA are constrained by non-availability of IT based<br />

monitoring system at the project level which is essential for effective monitoring.<br />

During the year 2009-10, a total <strong>thermal</strong> capacity of 9,106 MW was added against the programme of<br />

13,002 MW, which is the highest addition in any previous year. The private sector has responded enthusiastically<br />

to the opening up of the <strong>power</strong> market and a substantial amount of generating capacity is coming up through<br />

IPPs in coal, lignite, gas and hydro <strong>power</strong> projects. The private sector contributed 1,970 MW to <strong>thermal</strong><br />

generation capacity during period 2002-07. Since then <strong>thermal</strong> generation capacity of 5,920 MW has been<br />

commissioned in 11 th Plan and another about 16,266 MW <strong>thermal</strong> generation capacity is under construction in<br />

private sector. The private sector is likely to contribute substantial generating capacity in the 12 th Plan period<br />

(2012-17).<br />

Ultra Mega Power Projects (UMPPs) are being promoted by Ministry of Power with a view to provide <strong>power</strong><br />

to all at a reasonable rate and ensuring fast capacity addition as an initiative facilitating the <strong>development</strong> of<br />

UMPPs of 4,000 MW capacity each. Out of nine (9) UMPPs proposed to be set up in different states initially,<br />

four UMPPs one each in M.P., Gujarat, Andhra Pradesh and Jharkhand have been awarded and transferred to<br />

the developers selected through tariff based international competitive bidding and are at different stages of<br />

implementation. As per the present status of projects intimated by the developers, one unit of 660 MW of Sasan<br />

UMPP and two units of 800 MW each of Mundra UMPP are expected to be commissioned in 11 th Plan.<br />

CEA has been facilitating adoption of higher size units with supercritical technology. About 40 supercritical<br />

units of 660/800 MW are under construction and some of them would be commissioned in 11 th Plan itself.<br />

Initially supercritical units were designed with parameters of 247 kg/cm 2 , 537/565 0 C but now higher parameters<br />

of 247 kg/ cm 2 , 565/593 0 C are being adopted for new supercritical units. In 12 th Plan, supercritical units are likely<br />

to constitute a majority of coal based capacity addition. Efforts have been made to encourage International<br />

manufacturers to set up manufacturing facilities for Supercritical units in India so as to create indigenous<br />

manufacturing capability. As a result, four joint venture companies have been set up between international<br />

manufacturers and Indian companies for manufacturing supercritical boilers/turbo-generator in the country.<br />

To kick start the new joint ventures, bulk tendering of 11 Nos. 660 MW supercritical units of NTPC & DVC<br />

has been undertaken by NTPC through International Competitive Bidding (ICB) with the mandatory condition<br />

that the successful bidders would have to set up manufacturing facilities in India as per Phased Manufacturing<br />

Program (PMP) being specified in the bid document. CEA has been actively associated in the whole process and<br />

the progress of PMP would be monitored by a Committee under CEA.<br />

CEA/Ministry of Power had instituted a Comprehensive Award Scheme for efficient and economic operation of<br />

<strong>thermal</strong>, hydro and nuclear <strong>power</strong> stations, transmission system and <strong>power</strong> distribution companies as also for<br />

vii

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!