thermal power development - Infraline
thermal power development - Infraline
thermal power development - Infraline
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Central electricity authority Annual Report 2009-10<br />
from Govt. of India or Comfort Letter to this<br />
effect was made available to CEA. CEA found<br />
this project to be viable in case the project was<br />
funded on the aforesaid basis (90% grant). In the<br />
event of any change in the funding pattern, the<br />
project would require a fresh examination and<br />
Techno-economic Clearance for which the Govt.<br />
of Mizoram should revert back to CEA. One of<br />
the conditions stipulated in TEC letter was that<br />
if time gap between TEC and actual start of work<br />
is more than 3 years, a fresh TEC of the project<br />
would be required.<br />
Proposal for funding the project through<br />
various agencies was being pursued by the State<br />
Govt. On the request of State Govt., validity of<br />
TEC had been extended six times, last one being<br />
up to 8.11.2007.<br />
Govt. of Mizoram on 21.08.2007 requested<br />
for further extension of TEC indicating that<br />
Mizoram was seeking Viability Gap funding for<br />
the project. CEA observed that during the last<br />
seven years, more hydrological data would have<br />
become available necessitating reassessment of<br />
<strong>power</strong> potential. As the Cost Estimates were more<br />
than 7 years old, they needed revision. Moreover,<br />
Govt. of Mizoram proposed to adopt publicprivate<br />
partnership mode for implementation<br />
of the project, which would change the funding<br />
pattern as well as executing agency. Taking<br />
these factors in view, CEA did not consider it<br />
appropriate to grant further extension of validity<br />
of TEC. The Govt. of Mizoram was informed<br />
accordingly vide CEA letter dated 1.10.2007.<br />
11.6.3 Private Sector Projects<br />
A) CEA Concurred Projects:<br />
a) Demwe Lower HE Project (5x342 +<br />
1x40=1750 MW), Arunachal Pradesh<br />
by M/s ADPPL<br />
Demwe Lower HE Project was accorded<br />
concurrence by CEA on 20.11.2009 for<br />
an estimated cost of Rs. 13144.91 Crores<br />
(Completion Cost). MoEF has accorded<br />
Environmental Clearance to the project<br />
on 12.2.10. Forest Clearance is under<br />
process.<br />
Financial closure is yet to be achieved.<br />
b) Dibbin HE Project(2x60=120 MW),<br />
Arunachal Pradesh<br />
Dibbin HE Project was accorded<br />
concurrence by CEA on 04.12.2009 for<br />
an estimated cost of Rs. 728.54 Crores<br />
(Completion Cost). Environment and<br />
Forest Clearance is under process.<br />
Financial closure is yet to take place.<br />
c) Lower Siang HE Project (9x300=<br />
2700 MW), Arunachal Pradesh by<br />
M/s JAPL<br />
Lower Siang HE Project was<br />
accorded concurrence by CEA on<br />
15.02.2010 for an estimated cost of<br />
Rs. 19990.74 Crores (Completion Cost).<br />
Environment and Forest clearance is<br />
under process. Financial closure is yet<br />
to take place.<br />
11.6.4 H.E. Projects Allotted for<br />
implementation in the N.E.<br />
Region and yet to be taken up for<br />
construction<br />
A total of 92 H.E. Projects (above 25 MW<br />
capacity) with aggregate capacity of 39513 MW<br />
have been allotted in N.E. Region to Central and<br />
Private Sector for implementation in the near<br />
future and yet to be taken up for construction.<br />
Further 25 schemes with aggregate capacity of<br />
16175 MW have been identified which are yet<br />
to be allotted/ referred by State. Category-wise,<br />
these schemes are summarized below:<br />
"Electricity is life: Conserve it."<br />
125