Central electricity authority Annual Report 2009-10<br />

Annexure-6A<br />

(Item No.6.2)<br />

Status of Implementation of Ultra Mega Power Projects already awarded<br />

(1/2)<br />

S.No Name of UMPP Capacity<br />

(MW)<br />

Status<br />

1. Mundra UMPP 5 x 800 (i) Mundra UMPP was transferred to the selected developer namely Tata Power Ltd in April<br />

2007.<br />

(ii)<br />

(iii)<br />

(iv)<br />

(v)<br />

(vi)<br />

(vii)<br />

Financial closure for the project was achieved in April 2008.<br />

About 79% of the total land required (3224.6 acres) have been acquired.<br />

Further, transfer of 662 acres of Govt. land, requirement of which has subsequently, been<br />

indicated by the developer owing to change in alignment of outfall water channel, is under<br />

process by the Revenue Department.<br />

Order for main plant was placed in May 2007 for steam generators and in August 2007 for<br />

turbo generators. Orders for all major balance of plant packages have been placed<br />

Piling work for all boilers & turbo generators have been completed. Structural erection<br />

and Mechanical erection of Boilers is in progress. Work on TG building, main control<br />

building, chimney, general civil works and in other areas are in progress. The hydraulic<br />

test for boiler of unit-I completed in March, 2010.<br />

As per latest status first two units of 800 MW each are expected to be commissioning in<br />

11 th plan and remaining units in 12 th plan.<br />

2. Sasan UMPP 6x660 (i) Sasan UMPP was transferred to the selected developer namely Reliance Power Ltd in<br />

August 2007.<br />

(ii)<br />

(iii)<br />

(iv)<br />

(v)<br />

Financial closure for the project was achieved in April 2009.<br />

Out of total land requirement of 3484 acres for the <strong>power</strong> plant (including coal<br />

transportation system) about 64% has been acquired and acquisition for the remaining<br />

land is under process.<br />

Order for main plant was placed in June 2008. Orders for civil works in respect of Boilers,<br />

T.G, Main Building and CW system have been awarded and Orders for balance of plant<br />

are yet to be placed and are stated to be in progress.<br />

Construction of boundary wall, storage shed etc is in progress at site. Constructions of 376<br />

houses in R&R colony are completed with all Public facilities. Foundation work in Main<br />

Plant - Boiler is in progress, Chimney RCC shell is under construction.<br />

(vi) As per latest status first unit of 660 MW is expected to be commissioning in 11 th<br />

plan and<br />

remaining units in 12 th plan.<br />

168<br />

"CEA-Helping the Transformation of Indian Power Sector"