Central electricity authority Annual Report 2009-10<br />
Annexure-6A<br />
(Item No.6.2)<br />
Status of Implementation of Ultra Mega Power Projects already awarded<br />
(1/2)<br />
S.No Name of UMPP Capacity<br />
(MW)<br />
Status<br />
1. Mundra UMPP 5 x 800 (i) Mundra UMPP was transferred to the selected developer namely Tata Power Ltd in April<br />
2007.<br />
(ii)<br />
(iii)<br />
(iv)<br />
(v)<br />
(vi)<br />
(vii)<br />
Financial closure for the project was achieved in April 2008.<br />
About 79% of the total land required (3224.6 acres) have been acquired.<br />
Further, transfer of 662 acres of Govt. land, requirement of which has subsequently, been<br />
indicated by the developer owing to change in alignment of outfall water channel, is under<br />
process by the Revenue Department.<br />
Order for main plant was placed in May 2007 for steam generators and in August 2007 for<br />
turbo generators. Orders for all major balance of plant packages have been placed<br />
Piling work for all boilers & turbo generators have been completed. Structural erection<br />
and Mechanical erection of Boilers is in progress. Work on TG building, main control<br />
building, chimney, general civil works and in other areas are in progress. The hydraulic<br />
test for boiler of unit-I completed in March, 2010.<br />
As per latest status first two units of 800 MW each are expected to be commissioning in<br />
11 th plan and remaining units in 12 th plan.<br />
2. Sasan UMPP 6x660 (i) Sasan UMPP was transferred to the selected developer namely Reliance Power Ltd in<br />
August 2007.<br />
(ii)<br />
(iii)<br />
(iv)<br />
(v)<br />
Financial closure for the project was achieved in April 2009.<br />
Out of total land requirement of 3484 acres for the <strong>power</strong> plant (including coal<br />
transportation system) about 64% has been acquired and acquisition for the remaining<br />
land is under process.<br />
Order for main plant was placed in June 2008. Orders for civil works in respect of Boilers,<br />
T.G, Main Building and CW system have been awarded and Orders for balance of plant<br />
are yet to be placed and are stated to be in progress.<br />
Construction of boundary wall, storage shed etc is in progress at site. Constructions of 376<br />
houses in R&R colony are completed with all Public facilities. Foundation work in Main<br />
Plant - Boiler is in progress, Chimney RCC shell is under construction.<br />
(vi) As per latest status first unit of 660 MW is expected to be commissioning in 11 th<br />
plan and<br />
remaining units in 12 th plan.<br />