Central electricity authority Annual Report 2009-10<br />

CHAPTER – 11<br />

POWER DEVELOPMENT IN NORTH-EASTERN REGION<br />

11.1 Hydro-electric Potential in Northeastern<br />

Region<br />

As per Re-assessment Studies carried out by CEA,<br />

hydro potential of the North Eastern Region in<br />

terms of installed capacity has been estimated as<br />

58971 MW (58356 MW above 25 MW capacity).<br />

Out of the above, 1116 MW (above 25 MW<br />

capacity) have been harnessed so far while<br />

projects amounting to 2876 MW (above 25 MW<br />

capacity) are under construction. State-wise<br />

identified hydro-electric potential (above 25<br />

MW) of North-eastern Region and its status of<br />

<strong>development</strong> is given below:<br />

Region / State<br />

Identified potential as per<br />

Re-assessment Study (MW)<br />

Total<br />

(Above 25 MW)<br />

Capacity Developed<br />

(Above 25 MW)<br />

(MW)<br />

Capacity Under<br />

Construction<br />

(Above 25 MW)<br />

(MW)<br />

Meghalaya 2394 2298 156 166<br />

Tripura 15 0 0 0<br />

Manipur 1784 1761 105 0<br />

Assam 680 650 375 0<br />

Nagaland 1574 1574 75 0<br />

Arunachal Pradesh 50328 50064 405 2710<br />

Mizoram 2196 2131 0 0<br />

Total 58971 58356 1116 2876<br />

11.2 Survey & Investigation of Hydro<br />

Projects<br />

The Government approved a Three Stage<br />

Clearance procedure for hydro projects to be<br />

executed by CPSUs in consultation with MoF<br />

and MoEF. Under Stage-I, the CPSUs will<br />

incur expenditure on Survey & Investigation<br />

and preparation of Pre-feasibility Report.<br />

Under Stage-II, the CPSUs will undertake<br />

activities relating to detailed investigation<br />

and preparation of Detailed Project Report.<br />

During this Stage, pre-construction activities<br />

and infrastructure <strong>development</strong> including land<br />

acquisition will also be undertaken. Under<br />

Stage-III, approval of PIB/CCEA would be<br />

sought for investment decision in respect of<br />

construction of the projects.<br />

11.3 Preparation of DPRs under 50,000<br />

MW Hydro Initiative<br />

Ranking studies were earlier completed<br />

by CEA in October, 2001 in order to expedite<br />

hydro <strong>power</strong> <strong>development</strong> in the country in a<br />

systematic manner. Subsequently, Preliminary<br />

Feasibility Reports (PFRs) were prepared in<br />

respect of 62 schemes in NE region under<br />

“50,000 MW Hydro Electric Initiative”<br />

launched by Govt. of India in May, 2003. Low<br />

tariff H.E. schemes 17 Nos. (with first year<br />

tariff less than Rs.2.50/kWh) with aggregate<br />

capacity of 17,487 MW have been selected for<br />

taking up of detailed survey & investigation<br />

and preparation of DPR/ implementation. Out<br />

of these, DPR of 6 schemes namely Talong<br />

(225MW), Dibbin (120MW), Badao (70 MW),<br />