27.07.2014 Views

thermal power development - Infraline

thermal power development - Infraline

thermal power development - Infraline

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Central electricity authority Annual Report 2009-10<br />

among NHPC (69%), SJVNL (26%) and Govt.<br />

of Manipur (5%). Formation of Joint Venture is<br />

in progress.<br />

The project was techno-economically<br />

cleared by CEA vide its letter dated 2.7.2003<br />

at an estimated cost of Rs.5163.86 crores at<br />

December 2002 price level including IDC of<br />

Rs.757.26 crores. Part estimate of Rs.9.52 crores<br />

for undertaking some works on priority<br />

under Stage-II activities of the project was<br />

recommended by CEA on 2.04.2004.<br />

Revised Cost Estimates of the project<br />

were cleared by CEA for an amount of<br />

Rs.6701.97 crores including IDC of Rs.816.40<br />

crores at December 2004 price level on 6.05.2005.<br />

This estimate also included additional provision<br />

of Rs.1100.78 crores as Net Present Value (NPV)<br />

@ Rs.5.8 lakh per Hectare of submerged forest<br />

land converted for non-forestry use.<br />

First PIB meeting was held on 25.10.2005.<br />

As per the minutes of the meeting, MoP had<br />

to submit a Supplementary Note to be studied<br />

and considered in the Core Group of the PIB<br />

for finalizing its recommendations. Second<br />

PIB meeting was held on 31.01.2006 which<br />

recommended the project for placement before<br />

CCEA for consideration, subject to the following<br />

observations:<br />

i) Costs relating to flood moderation, diversion<br />

of National Highways and external security<br />

may be borne by the concerned administrative<br />

departments. The costs should be updated<br />

and availability of funds confirmed in the<br />

Note for CCEA.<br />

ii) Ministry of Power may take up the issue of<br />

high NPV cost with the MoE&F and reflect<br />

the outcome in the Note for CCEA.<br />

iii) Ministry of Power may persuade the State<br />

Governments of Mizoram and Manipur to<br />

reduce their share of free <strong>power</strong> from the<br />

project.<br />

iv) Project costs may be updated to December<br />

2005 price level.<br />

v) Ministry of Power would obtain Environment<br />

and Forest Clearance before submitting the<br />

proposal for consideration of CCEA.<br />

vi) Risks relating to law and order and R&R to<br />

be explained clearly in the CCEA Note, along<br />

with strategies for risk mitigation. Views of<br />

Manipur and Mizoram Governments in this<br />

regard to be brought on record.<br />

vii) PPAs may be firmed up before the project is<br />

submitted for consideration of CCEA.<br />

viii) Adequacy of technical investigations,<br />

including critical design parameters, may be<br />

confirmed by the project authority to avoid<br />

any future surprises.<br />

As per PIB observations, following actions have<br />

been taken:<br />

i) The updated Revised Cost Estimates<br />

submitted by NEEPCO to CEA at November,<br />

2005 price level were vetted by CEA on<br />

22.03.2006 as Rs.5026.84 crores (as hard<br />

cost excluding IDC, flood moderation,<br />

diversion of National Highway and external<br />

security). Subsequently, CEA vetted the IDC<br />

component as Rs.828.99 crores (November,<br />

2005 price level) in August, 2006. Thus,<br />

the total cost at November, 2005 price level<br />

works out to Rs.5855.83 crores. This cost<br />

did not include the cost of flood moderation,<br />

diversion of National Highway and external<br />

security.<br />

ii) In a meeting taken by Secretary (Power)<br />

on 26.2.2008 in MoP, NEEPCO indicated<br />

that MoWR on 15.12.2005 had conveyed<br />

approval for meeting cost of flood<br />

component. Ministry of Shipping, Road<br />

Transport and Highways conveyed their<br />

‘In Principle Approval’ to meet cost of<br />

National Hightway diversion on 14.9.2006.<br />

MHA conveyed ‘In Principle Approval’ on<br />

120<br />

"CEA-Helping the Transformation of Indian Power Sector"

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!