Central electricity authority Annual Report 2009-10<br />
6.11.5 Overall LE / R&M Status during<br />
11 th Plan (From April 2007 to<br />
March 2010)<br />
Out of 53 units (7318 MW) for LE works<br />
and 76 units (18965 MW) for R&M works<br />
planned for 11 th Plan, LE works in 10 units<br />
(851 MW) and R&M works in 56 units (14610<br />
MW) were completed during the first three years<br />
of the 11 th Plan. Gist of LE and R&M works<br />
completed during the 11 th Plan (till March 2010)<br />
are tabulated below:<br />
Sl. No. Particulars State sector Central sector Total<br />
(State + Central )<br />
A) LE works<br />
1. Completed during 11 th<br />
Plan (till March 2010)<br />
No. of<br />
units<br />
Capacity<br />
(MW)<br />
No. of<br />
units<br />
Capacity<br />
(MW)<br />
No. of<br />
units<br />
Capacity<br />
(MW)<br />
7 584 3 267 10 851<br />
B) R&M works<br />
Completed during 11 th 18 4350 38 10260 56 14610<br />
Plan (till March 2010)<br />
Total 25 4934 41 10527 66 15461<br />
6.12 Target vis-à-vis Achievement for<br />
LE / R&M Programme during the<br />
first three years of the 11 th Plan<br />
Out of 129 units planned for LE/R&M<br />
works during 11 th Plan (60 units in State Sector<br />
and 69 units in Central Sector with a capacity<br />
26,283 MW), LE/R&M works in respect of<br />
66 units (25 in State Sector and 41 in Central<br />
Sector) of total capacity of 15,461 MW were<br />
completed (till March, 2010). In addition, 4 units<br />
of Talcher TPS of 60 MW each which were not<br />
originally envisaged for R&M works in National<br />
Perspective Plan, were also completed. In terms<br />
of units as well as capacity, 52% and 59% of<br />
targets planned for 11 th Plan have been achieved<br />
respectively during the first three years of the<br />
11 th Plan.<br />
Further, out of remaining 63 units, Life<br />
Extension / R&M works are to be completed<br />
in respect of 56 units of total capacity of<br />
9552 MW during remaining period of 2<br />
years of the 11 th Plan and further LE works<br />
on another 7 units in the State Sector of total<br />
capacity of 1270 MW are likely to slip beyond<br />
11 th Plan.<br />
6.12.1 Main Reasons of shortfall in<br />
achieving LE / R&M targets<br />
• In <strong>power</strong> deficits scenario, utilities hesitate<br />
to take longer shut down for undertaking LE<br />
works.<br />
• Delay in supplies of equipment by the<br />
suppliers.<br />
• Shortage of BoP suppliers/contractors in the<br />
country.<br />
• Non-availability of dedicated R&M team<br />
with most of the SEBs /PSUs.<br />
• Lack of co-ordination between the<br />
contractors and their sub-contractors.<br />
• Surprises, when the unit is opened up<br />
for carrying out the R&M/LE works,<br />
new defects or damaged components are<br />
observed resulting in delay in procurement<br />
& rectification.<br />