Central electricity authority Annual Report 2009-10<br />

6.11.5 Overall LE / R&M Status during<br />

11 th Plan (From April 2007 to<br />

March 2010)<br />

Out of 53 units (7318 MW) for LE works<br />

and 76 units (18965 MW) for R&M works<br />

planned for 11 th Plan, LE works in 10 units<br />

(851 MW) and R&M works in 56 units (14610<br />

MW) were completed during the first three years<br />

of the 11 th Plan. Gist of LE and R&M works<br />

completed during the 11 th Plan (till March 2010)<br />

are tabulated below:<br />

Sl. No. Particulars State sector Central sector Total<br />

(State + Central )<br />

A) LE works<br />

1. Completed during 11 th<br />

Plan (till March 2010)<br />

No. of<br />

units<br />

Capacity<br />

(MW)<br />

No. of<br />

units<br />

Capacity<br />

(MW)<br />

No. of<br />

units<br />

Capacity<br />

(MW)<br />

7 584 3 267 10 851<br />

B) R&M works<br />

Completed during 11 th 18 4350 38 10260 56 14610<br />

Plan (till March 2010)<br />

Total 25 4934 41 10527 66 15461<br />

6.12 Target vis-à-vis Achievement for<br />

LE / R&M Programme during the<br />

first three years of the 11 th Plan<br />

Out of 129 units planned for LE/R&M<br />

works during 11 th Plan (60 units in State Sector<br />

and 69 units in Central Sector with a capacity<br />

26,283 MW), LE/R&M works in respect of<br />

66 units (25 in State Sector and 41 in Central<br />

Sector) of total capacity of 15,461 MW were<br />

completed (till March, 2010). In addition, 4 units<br />

of Talcher TPS of 60 MW each which were not<br />

originally envisaged for R&M works in National<br />

Perspective Plan, were also completed. In terms<br />

of units as well as capacity, 52% and 59% of<br />

targets planned for 11 th Plan have been achieved<br />

respectively during the first three years of the<br />

11 th Plan.<br />

Further, out of remaining 63 units, Life<br />

Extension / R&M works are to be completed<br />

in respect of 56 units of total capacity of<br />

9552 MW during remaining period of 2<br />

years of the 11 th Plan and further LE works<br />

on another 7 units in the State Sector of total<br />

capacity of 1270 MW are likely to slip beyond<br />

11 th Plan.<br />

6.12.1 Main Reasons of shortfall in<br />

achieving LE / R&M targets<br />

• In <strong>power</strong> deficits scenario, utilities hesitate<br />

to take longer shut down for undertaking LE<br />

works.<br />

• Delay in supplies of equipment by the<br />

suppliers.<br />

• Shortage of BoP suppliers/contractors in the<br />

country.<br />

• Non-availability of dedicated R&M team<br />

with most of the SEBs /PSUs.<br />

• Lack of co-ordination between the<br />

contractors and their sub-contractors.<br />

• Surprises, when the unit is opened up<br />

for carrying out the R&M/LE works,<br />

new defects or damaged components are<br />

observed resulting in delay in procurement<br />

& rectification.<br />

74<br />