27.07.2014 Views

thermal power development - Infraline

thermal power development - Infraline

thermal power development - Infraline

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Central electricity authority Annual Report 2009-10<br />

Uprating (LE&U) of <strong>thermal</strong> <strong>power</strong> stations<br />

upto the year 2016-17”. This document also<br />

includes revised guidelines for Renovation &<br />

Modernization /Life Extensions works on coal /<br />

lignite based <strong>thermal</strong> <strong>power</strong> stations and this<br />

document was released by Honorable Minister<br />

of Power on 14.12.2009 on the occasion of<br />

Energy Conservation Day.<br />

In the Perspective Plan, 53 units<br />

(7318 MW) for LE works and 76 units (18965<br />

MW) for R&M works have been identified in<br />

11 th Plan and for 12 th Plan 72 units (16532 MW)<br />

for LE work and 23 units (4871 MW) for R&M<br />

work have been identified.<br />

6.11 Life Extension / R&M Programme<br />

6.11.1 LE/R&M Programme during 11 th<br />

Plan (2007-08 to 2011-12)<br />

Status of implementation of LE & R&M<br />

works during 11 th Plan as on 31 st March, 2010<br />

is furnished at Annexure-6E & Annexure-6F<br />

respectively. Break up of units identified for LE /<br />

R&M works during 11 th Plan State Sector-wise<br />

and Central Sector-wise is furnished as under :<br />

Sl<br />

No.<br />

Particular State Sector Central Sector Total (State sector +<br />

Central Sector<br />

No. of units<br />

Capacity<br />

(MW)<br />

No. of<br />

units<br />

Capacity<br />

(MW)<br />

No. of<br />

units<br />

Capacity<br />

(MW)<br />

1. LE works 33 4524 20 2794 53 7318<br />

2. R&M works 27 6015 49 12950 76 18965<br />

Total 60 10539 69 15744 129 26283<br />

6.11.2 Estimated funds requirements for<br />

LE and R&M programme during<br />

11 th Plan<br />

The estimated fund requirements for LE and<br />

R&M programme for 11 th Plan is Rs. 16920 crores,<br />

comprising Rs. 12433 crores and Rs. 4487 crores<br />

for LE and R&M programme respectively, as<br />

would be seen from the table given below:-<br />

Sl.<br />

No.<br />

Particulars of Works No. of TPSs No. of Units Capacity<br />

(MW)<br />

Estimated<br />

Cost(Rs. Crores)<br />

1 L.E. Program 23 53 7318 12433<br />

2 R&M Program 21 76 18965 4487<br />

Total 16920<br />

6.11.3 Life Extension Programme Status<br />

during 2007-08 to 2009-10 of the<br />

11 th Plan<br />

During the first three years of 11 th Plan (till<br />

March 2010), LE works have been completed in<br />

10 units comprising 7 units in the State Sector<br />

and 3 units of NTPC in the Central Sector out<br />

of total 53 units planned for 11 th Plan. Sectorwise<br />

details of units where LE works have been<br />

completed are furnished as under:<br />

72<br />

"CEA-Helping the Transformation of Indian Power Sector"

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!