Central electricity authority Annual Report 2009-10<br />
for 9 th , 10 th and 11 th Plans with 117 schemes<br />
having an aggregate installed capacity of<br />
19370 MW with benefit of 7755MW at an<br />
estimated cost of Rs.4654 crores.<br />
5.11.1 8 th , 9 th & 10 th Plan Achievements<br />
Under the hydro R&M programme,<br />
65 (15 in Central Sector and 50 in State<br />
Sector) hydro-electric schemes (13 upto the<br />
8 th Plan, 20 in the 9 th Plan and 32 in the 10 th<br />
Plan) with an installed capacity of 10511<br />
MW at a cost of Rs.1,726 Crores have been<br />
completed by the end of the 10 th Plan (i.e. by<br />
31.03.2007) and have accrued a benefit of<br />
2351 MW through Life Extension, Uprating<br />
and Restoration.<br />
5.11.2 11 th & 12 th Plan Programme<br />
At the beginning of 11 th Plan i.e. May/<br />
June, 2007, a total of 62 hydro R&M schemes<br />
were programmed with an installed capacity<br />
of about 11340 MW at an estimated cost of<br />
Rs. 4035 Crs. to accrue a benefit of about<br />
4393 MW through life extension, uprating<br />
and restoration. The programme was finalized<br />
in consultation with SEBs/Utilities.<br />
During Dec., 2007, Two (2) hydro<br />
R&M schemes of Rajasthan having Inter-<br />
State issues were dropped due to disagreement<br />
between Rajasthan and Madhya Pradesh.<br />
Further, three (3) schemes of APGENCO<br />
namely Hampi, Machkund and Tungbhadra;<br />
One scheme of TNEB namely Sholayar-I and<br />
one scheme of KPCL namely Bhadra were<br />
shifted to 12 th Plan on the request of Project<br />
Authorities as the generating units were<br />
running satisfactorily. Also, one scheme<br />
of BBMB namely Dehar was split into two<br />
schemes Dehar Ph. A and Dehar Ph.B. Thus,<br />
presently 56 hydro R&M schemes having<br />
an installed capacity of about 10810 MW<br />
at a revised/updated estimated cost of<br />
Rs. 4203 Crores programmed to accrue<br />
a benefit of about 4099 MW through life<br />
extension, uprating and restoration are under<br />
implementation.<br />
Annual review meetings were held<br />
with various utilities in CEA during March/<br />
April,2010. As per the outcome of discussions,<br />
one scheme namely Bhadra HEP of KPCL has<br />
been declared as completed. Now 29 schemes<br />
are planned for implementation during the<br />
11 th Plan.<br />
Till date (as on 31.03.2010), 13<br />
Schemes (out of 29 targeted schemes) with<br />
an installed capacity of 3204 MW at a cost<br />
of about Rs. 205 Crores have been completed<br />
and have accrued a benefit of 380 MW through<br />
life extension & uprating. The R&M works<br />
on balance 16 ongoing schemes (installed<br />
capacity 4684 MW) are under various stages<br />
of implementation i.e. Ongoing, Tendering,<br />
DPR preparation, finalization and RLA<br />
Studies etc.<br />
Further, 26 more hydro schemes<br />
planned for implementation in 11 th Plan have<br />
now been shifted to 12 th Plan (envisaging<br />
8 R&M schemes), as RLA studies of these<br />
schemes could not be completed or units are<br />
running comparatively satisfactorily. Also, a<br />
new R&M scheme of Rengali HPS has been<br />
proposed by OHPC for completion in 12 th<br />
Plan. Thus, a total of 35 schemes are now<br />
envisaged for completion during 12 th Plan.<br />
After completion of the R&M works of these<br />
projects, having total installed capacity of<br />
3183 MW, there will be a benefit of 2795<br />
MW through Life Extension & Uprating<br />
at an estimated cost of Rs. 3075 Crores<br />
(provisional).<br />
60<br />
"CEA-Helping the Transformation of Indian Power Sector"