27.07.2014 Views

thermal power development - Infraline

thermal power development - Infraline

thermal power development - Infraline

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Central electricity authority Annual Report 2009-10<br />

various Sub-station equipment of 220 kV and<br />

above voltage class, investigation in respect<br />

of the following utilities was carried out and<br />

recommendation sent to concerned utility:<br />

a) Failure of two 400/220/33 kV, 315 MVA<br />

transformers in Mandola Substation of<br />

PGCIL.<br />

b) Failure of 220/66-33 kV, 100 MVA<br />

transformer in Park Street Substation of<br />

Delhi Transco Ltd.<br />

c) Failure of 220/66-33 kV, 100 MVA<br />

transformer in Baddi Substation of HPSEB.<br />

3.12 Technology Improvement<br />

Programme in Power System<br />

After completion of training at Chicago,<br />

USA, following Pilot Project was taken up with<br />

SEBs in following area:<br />

i) Residual Life Assessment (RLA) of<br />

Substation Equipment<br />

Construction of any transmission system<br />

requires a huge amount of investment and<br />

the cost of EHV Substation equipment<br />

contributes a major portion of cost of the<br />

transmission system. As the transmission<br />

lines and substations are growing older,<br />

there is a need of proper condition<br />

monitoring of substation equipment to<br />

assess the residual life of various substation<br />

equipment and ensure proper maintenance<br />

of the equipment. A pilot project on<br />

“Residual Life Assessment of Substation<br />

Equipment” has been taken up with the<br />

MSEB(now MSETCL).<br />

Following diagnostic tools have been<br />

procured and installed in 220/33 kV<br />

Mudsighi, 400/220kV Kolhapur-II<br />

Substation of MSETCL at Kolhapur:<br />

i) Digital Earth Tester<br />

ii) Transformer Winding Resistance<br />

Meter<br />

iii) Contact Resistance Meter<br />

iv) Automatic relay test kit (3 phase)<br />

v) Circuit Breaker Operation Analyzer<br />

vi) Leakage current monitor for lightning<br />

arrester<br />

vii) Automatic Capacitance & Tan Delta<br />

Measuring Equipment.<br />

In addition to above, the following<br />

equipment are being utilized in GETCO,<br />

Ahmedabad. The following diagnostic tools<br />

which were earlier used in MSETCL are at<br />

present being utilized by GETCO, Ahmedabad:<br />

1) On-line Dissolved gas Analyzer for<br />

Transformer<br />

2) Partial Discharge Measuring Equipment for<br />

Transformer<br />

3) Frequency Response Analyzer for<br />

Transformer<br />

3.13 Construction Monitoring of<br />

Transmission Projects<br />

The monitoring of construction of<br />

transmission lines and sub-stations at voltage<br />

levels of 220 kV and above is being carried out<br />

with a view to achieve completion of transmission<br />

system both to ensure evacuation of <strong>power</strong> from<br />

new Generating Stations as well as to strengthen<br />

the <strong>power</strong> system network in the country.<br />

For the year 2009-10, programme for<br />

stringing of 280 Ckm at +500 kV HVDC,<br />

632 Ckm of 765 kV, 9548 Ckm of 400 kV<br />

and 7103 Ckm of 220 kV transmission lines<br />

was envisaged. Against this programme, the<br />

stringing of transmission lines actually achieved<br />

during the year 2009-10 was 280 Ckm of +500<br />

kV HVDC, 445 Ckm of 765 kV, 7857 Ckm of<br />

400 kV and 5139 Ckm of 220 kV lines. Details<br />

of transmission lines completed during the year<br />

2009-10 are given in Annexure-3C.<br />

Voltage-wise / Sector-wise actual<br />

achievement vis-à-vis programme for the year<br />

"CEA-Helping the Transformation of Indian Power Sector"<br />

39

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!