thermal power development - Infraline
thermal power development - Infraline
thermal power development - Infraline
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Central electricity authority Annual Report 2009-10<br />
various Sub-station equipment of 220 kV and<br />
above voltage class, investigation in respect<br />
of the following utilities was carried out and<br />
recommendation sent to concerned utility:<br />
a) Failure of two 400/220/33 kV, 315 MVA<br />
transformers in Mandola Substation of<br />
PGCIL.<br />
b) Failure of 220/66-33 kV, 100 MVA<br />
transformer in Park Street Substation of<br />
Delhi Transco Ltd.<br />
c) Failure of 220/66-33 kV, 100 MVA<br />
transformer in Baddi Substation of HPSEB.<br />
3.12 Technology Improvement<br />
Programme in Power System<br />
After completion of training at Chicago,<br />
USA, following Pilot Project was taken up with<br />
SEBs in following area:<br />
i) Residual Life Assessment (RLA) of<br />
Substation Equipment<br />
Construction of any transmission system<br />
requires a huge amount of investment and<br />
the cost of EHV Substation equipment<br />
contributes a major portion of cost of the<br />
transmission system. As the transmission<br />
lines and substations are growing older,<br />
there is a need of proper condition<br />
monitoring of substation equipment to<br />
assess the residual life of various substation<br />
equipment and ensure proper maintenance<br />
of the equipment. A pilot project on<br />
“Residual Life Assessment of Substation<br />
Equipment” has been taken up with the<br />
MSEB(now MSETCL).<br />
Following diagnostic tools have been<br />
procured and installed in 220/33 kV<br />
Mudsighi, 400/220kV Kolhapur-II<br />
Substation of MSETCL at Kolhapur:<br />
i) Digital Earth Tester<br />
ii) Transformer Winding Resistance<br />
Meter<br />
iii) Contact Resistance Meter<br />
iv) Automatic relay test kit (3 phase)<br />
v) Circuit Breaker Operation Analyzer<br />
vi) Leakage current monitor for lightning<br />
arrester<br />
vii) Automatic Capacitance & Tan Delta<br />
Measuring Equipment.<br />
In addition to above, the following<br />
equipment are being utilized in GETCO,<br />
Ahmedabad. The following diagnostic tools<br />
which were earlier used in MSETCL are at<br />
present being utilized by GETCO, Ahmedabad:<br />
1) On-line Dissolved gas Analyzer for<br />
Transformer<br />
2) Partial Discharge Measuring Equipment for<br />
Transformer<br />
3) Frequency Response Analyzer for<br />
Transformer<br />
3.13 Construction Monitoring of<br />
Transmission Projects<br />
The monitoring of construction of<br />
transmission lines and sub-stations at voltage<br />
levels of 220 kV and above is being carried out<br />
with a view to achieve completion of transmission<br />
system both to ensure evacuation of <strong>power</strong> from<br />
new Generating Stations as well as to strengthen<br />
the <strong>power</strong> system network in the country.<br />
For the year 2009-10, programme for<br />
stringing of 280 Ckm at +500 kV HVDC,<br />
632 Ckm of 765 kV, 9548 Ckm of 400 kV<br />
and 7103 Ckm of 220 kV transmission lines<br />
was envisaged. Against this programme, the<br />
stringing of transmission lines actually achieved<br />
during the year 2009-10 was 280 Ckm of +500<br />
kV HVDC, 445 Ckm of 765 kV, 7857 Ckm of<br />
400 kV and 5139 Ckm of 220 kV lines. Details<br />
of transmission lines completed during the year<br />
2009-10 are given in Annexure-3C.<br />
Voltage-wise / Sector-wise actual<br />
achievement vis-à-vis programme for the year<br />
"CEA-Helping the Transformation of Indian Power Sector"<br />
39