Central electricity authority Annual Report 2009-10<br />

It may be seen from above that the gas<br />

supply for gas based <strong>power</strong> stations has been<br />

inadequate. It was enough to operate these<br />

stations at about 52 % PLF only during 2007-08.<br />

Similarly, the average gas supply during 2008-09<br />

was 37.45 MMSCMD, against the requirement<br />

of 66.61 MMSCMD to operate the stations at<br />

90% PLF, which was sufficient to operate these<br />

stations at about 50.6% PLF.<br />

*****<br />

The production of gas from KG basin<br />

(D-6) has started from April 2009 and hence<br />

the gas supply to Gas based GT stations has<br />

improved since then. The average gas supply<br />

during the year 2009-10 was 55.45 MMSCMD,<br />

against the requirement of 78.09 MMSCMD (as<br />

on 31.3.2010) to operate the stations at 90% PLF,<br />

which was sufficient to operate these stations at<br />

about 63.98% PLF.<br />

Mundra Power Project<br />

"Energy Saved is Energy Generated"<br />

31