Central electricity authority Annual Report 2009-10<br />

Name of State<br />

Summary of H.E Projects (above 25 MW capacity) in the N.E. Region<br />

(yet to be taken up for construction)<br />

No.<br />

Central Private Unallocated/State Total<br />

I.C.<br />

(MW)<br />

No.<br />

I.C.<br />

(MW)<br />

No. I.C. (MW) No.<br />

I.C.<br />

(MW)<br />

Ar. Pradesh 4 5870 75 29512 8 14785 87 50167<br />

Assam - - - - 5 360 5 360<br />

Manipur 2 1566 - - 3 195 5 1761<br />

Meghalaya 1 90 7 1745 7 635 15 2470<br />

Mizoram 3 730 - - 1 60 4 790<br />

Nagaland - - - - 1 140 1 140<br />

Total (NER) 10 8256 82 31257 25 16175 117 55688<br />

11.7 Status of Construction of Thermal<br />

Power Projects in North-eastern<br />

Region<br />

The progress of various <strong>thermal</strong> <strong>power</strong><br />

projects under construction in North-eastern<br />

Region is given below:<br />

a) Lakwa Waste Heat Recovery Project<br />

(Steam Turbine -37.2 MW):<br />

The project is being executed by Assam<br />

Power Generating Company Limited in the<br />

Sibsagar District of Assam State. EPC contract<br />

was placed on M/s BHEL in March, 2010. The<br />

project progress has been delayed due to very<br />

slow progress on civil construction front. The<br />

project is now targeted for commissioning in<br />

October 2010.<br />

b) Bongaigaon TPS (3x250MW):<br />

Project is being executed by M/s NTPC<br />

at Salakati, Kokrajhar District of Assam. MoEF<br />

clearance has been obtained and coal linkage<br />

for the project has been accorded by Ministry<br />

of Coal. Order of Main Plant Package has been<br />

placed on M/s BHEL in February, 2008. Boiler<br />

drum has been lifted in January, 2010 and<br />

Condenser erection is also under progress for<br />

Unit-1. Boiler erection has started for Unit-2 in<br />

March, 2010 and for Unit-3, it is expected to start<br />

by June, 2010. The constraints being faced in<br />

project execution include slow progress of civil<br />

works and law & order problem. The anticipated<br />

dates of commissioning for Unit-1, 2 & 3 are<br />

July, 2011, January, 2012 and March, 2012 (Best<br />

Effort Basis) respectively.<br />

c) Tripura CCPP (2x 363.3 MW):<br />

Project is being executed by joint venture<br />

of ONGC, Govt. of Tripura & Infrastructure<br />

Leasing and Finance Services (IL&FS) at<br />

Palatana, Tripura. Main Plant Order has been<br />

placed on M/s BHEL in June, 2008. Project is<br />

delayed due to problem in transportation of heavy<br />

equipments to site, transmission lines/ <strong>power</strong><br />

evacuation/ start-up <strong>power</strong> and finalization of<br />

Feasibility Report for infrastructure requirement<br />

for use of Ashuganj Port & land route in<br />

Bangladesh to reduce time of transportation of<br />

machinery to site. The project is likely to be<br />

commissioned in 12 th Plan.<br />

d) Baramura Gas Based Project, Unit-5<br />

(1x21 MW)<br />

The project is an extension unit being<br />

executed by Tripura State Electricity<br />

Corporation Ltd. (TSECL) in District<br />

Agartala, Tripura. EPC contract was awarded to<br />

M/s BHEL in March, 2008 with a target date of<br />

commissioning as November, 2009. The project<br />

is now likely to be commissioned by June, 2010.<br />