Project Description<br />

WMATA <strong>FY2017</strong> Capital Project Summary<br />

CIP0022 Track Structural Rehabilitation<br />

This project rehabilitates structural components and<br />

restores elevated platforms, bridges and retaining walls to<br />

designed load carrying capacity. The goals are based on<br />

annual inspections and critical engineering assessments, as<br />

the loss of one of these structures could affect an entire<br />

Metrorail line segment.<br />

Deliverables<br />

1) Torque 500 bolts annually. Rehabilitate 1,200 square feet<br />

of concrete<br />

2) Replace 800 deck joints annually<br />

Proposed <strong>FY2017</strong> Budget<br />

Appendix A<br />

Financial Summary<br />

$8,000,000<br />

$6,000,000<br />

$4,000,000<br />

$2,000,000<br />

$0<br />

FY2016<br />

<strong>FY2017</strong><br />

FY2018<br />

FY2019<br />

FY2020<br />

FY2021<br />

FY2022<br />

Milestones<br />

1) This is an on‐going program to replace 800 deck joints,<br />

torque 500 bolts and rehabilitate 1,200 square feet of<br />

concrete. In FY2018 the scope of work and deliverables will<br />

increase considerably due to expanded project goals<br />

and an increase of workforce due to a second team being<br />

implemented<br />

Project Financials<br />

FY2016 ‐ FY2011 ‐<br />

Budget (in 000s) FY11‐FY15 FY2016 <strong>FY2017</strong> FY2018 FY2019 FY2020 FY2021 FY2022 FY2022 FY2022<br />

PPersonnel 8,299 1,960 1,935 5,798 6,066 6,348 6,643 6,955 35,704 44,004<br />

NNon‐Personnel 4,482 198 164 493 518 544 571 600 3,089 7,571<br />

Total Budget 12,781 2,158 2,099 6,292 6,584 6,892 7,215 7,554 38,793 51,575<br />

Planned Funding Sources<br />

As of 12/16/2015<br />

<strong>FY2017</strong><br />

Original<br />

FY11‐FY16<br />

Cost<br />

Current<br />

FY11 ‐ FY16<br />

Cost<br />

Variance Analysis<br />

Increase in both labor and materials to<br />

deliver additional scope have resulted in<br />

higher costs<br />

NPRIIA<br />

2,099<br />

Total 2,099<br />

12,268 15,006<br />