Project Description<br />

WMATA <strong>FY2017</strong> Capital Project Summary<br />

CIP0185 Escalator Replacement<br />

This project will replace the oldest and poorest performing<br />

escalators in the system as needed to maintain escalator<br />

safety, availability and reliability. The new escalators will be<br />

equipped with more energy efficient devices and<br />

capabilities. This program will result in the replacement of<br />

approximately 128 escalators at 34 stations. Fourteen of<br />

the originally planned replacements under this project will<br />

now be done as major rehabilitations.<br />

Deliverables<br />

Proposed <strong>FY2017</strong> Budget<br />

Appendix A<br />

1) Replace approximately 22 escalators, projected locations<br />

are: Bethesda, Woodley Park, Van Ness, Georgia Avenue,<br />

Columbia, Waterfront, Arlington<br />

Cemetery, Capitol Heights, Smithsonian, Glenmont, Shaw,<br />

Minnesota Avenue<br />

Financial Summary<br />

$40,000,000<br />

$30,000,000<br />

Milestones<br />

1) Complete current contract to repair 128 escalators (20<br />

annually) by FY2020<br />

$20,000,000<br />

$10,000,000<br />

$0<br />

FY2016<br />

<strong>FY2017</strong><br />

FY2018<br />

FY2019<br />

FY2020<br />

FY2021<br />

FY2022<br />

Project Financials<br />

FY2016 ‐ FY2011 ‐<br />

Budget (in 000s) FY11‐FY15 FY2016 <strong>FY2017</strong> FY2018 FY2019 FY2020 FY2021 FY2022 FY2022 FY2022<br />

PPersonnel 10,425 8,932 9,351 10,477 10,775 11,011 0 0 50,547 60,972<br />

NNon‐Personnel 35,666 21,120 18,488 24,469 24,139 24,863 0 0 113,079 148,745<br />

Total Budget 46,091 30,052 27,840 34,946 34,914 35,874 0 0 163,626 209,717<br />

Planned Funding Sources<br />

As of 12/16/2015<br />

<strong>FY2017</strong><br />

Original<br />

FY11‐FY16<br />

Cost<br />

Current<br />

FY11 ‐ FY16<br />

Cost<br />

Variance Analysis<br />

The estimated cost to replace escalators<br />

has increased due to new safety<br />

requirements for all deep stations<br />

NPRIIA<br />

27,840<br />

Total 27,840<br />

0 76,748<br />

A-103