WMATA <strong>FY2017</strong> Capital Project Summary<br />

CIP0084 Southern Avenue Bus Garage Replacement<br />

Project Description<br />

This project will replace the existing Southern Avenue Bus<br />

Garage with a fully modern Leadership in Energy and<br />

Environmental Design (LEED) Silver facility that can hold 175<br />

buses. The existing facility is over 90 years old. This project<br />

also includes the construction of a new heavy repair and<br />

overhaul facility. The total estimated cost of this project is<br />

approximately $132 million.<br />

Deliverables<br />

1) Site Utilities installation complete ‐ May 2017<br />

Proposed <strong>FY2017</strong> Budget<br />

Appendix A<br />

2) Structural Framing and Decking construction complete ‐<br />

December 2016<br />

3) Roofing Structural Installation complete ‐ June 2017<br />

4) Side Concrete Paving work complete ‐ June 2017<br />

Financial Summary<br />

$80,000,000<br />

$60,000,000<br />

$40,000,000<br />

Milestones<br />

1) Construction of new facility estimated completion ‐<br />

September 2018<br />

2) Demolition of old Bus Garage to begin ‐ January 2021<br />

$20,000,000<br />

$0<br />

FY2016<br />

<strong>FY2017</strong><br />

FY2018<br />

FY2019<br />

FY2020<br />

FY2021<br />

FY2022<br />

3) Demolition and remediation of old Bus Garage estimated<br />

completion ‐ September 2023<br />

Project Financials<br />

FY2016 ‐ FY2011 ‐<br />

Budget (in 000s) FY11‐FY15 FY2016 <strong>FY2017</strong> FY2018 FY2019 FY2020 FY2021 FY2022 FY2022 FY2022<br />

PPersonnel 1,607 2,850 2,541 6,907 3,911 1,943 486 1,612 20,251 21,858<br />

NNon‐Personnel 35,214 25,806 28,863 58,547 6,336 3,057 743 1,076 124,427 159,641<br />

Total Budget 36,821 28,656 31,404 65,454 10,247 5,000 1,229 2,688 144,678 181,499<br />

Planned Funding Sources<br />

As of 12/16/2015<br />

<strong>FY2017</strong><br />

Original<br />

FY11‐FY16<br />

Cost<br />

Current<br />

FY11 ‐ FY16<br />

Cost<br />

Variance Analysis<br />

Due to delays in site selection and<br />

permitting process, the project<br />

expenditures have shifted to later years<br />

NDebt<br />

31,404<br />

Total 31,404<br />

113,258 65,864<br />

A-55