Project Description<br />

WMATA <strong>FY2017</strong> Capital Project Summary<br />

CIP0139_S4 Eliminate Work Order Backlog<br />

Due to lack of track time, WMATA’s maintenance<br />

departments must consistently re‐schedule work, resulting<br />

in growing maintenance backlogs, dating back to 2012 and<br />

2013. This project addresses FTA SMI R‐3‐25‐a.<br />

Deliverables<br />

1) Provide narrative for reestablishment of the Defect<br />

Report<br />

2) Provide a detailed staffing plan and explanation<br />

Proposed <strong>FY2017</strong> Budget<br />

Appendix A<br />

Financial Summary<br />

$250,000<br />

$200,000<br />

$150,000<br />

$100,000<br />

$50,000<br />

$0<br />

Milestones<br />

1) Submit to FTA for consideration of closure in FY2016<br />

FY2016<br />

<strong>FY2017</strong><br />

FY2018<br />

FY2019<br />

FY2020<br />

FY2021<br />

FY2022<br />

Project Financials<br />

FY2016 ‐ FY2011 ‐<br />

Budget (in 000s) FY11‐FY15 FY2016 <strong>FY2017</strong> FY2018 FY2019 FY2020 FY2021 FY2022 FY2022 FY2022<br />

PPersonnel 0 67 0 0 0 0 0 0 67 67<br />

NNon‐Personnel 0 145 0 0 0 0 0 0 145 145<br />

Total Budget 0 212 0 0 0 0 0 0 212 212<br />

Planned Funding Sources<br />

As of 12/16/2015<br />

<strong>FY2017</strong><br />

Original<br />

FY11‐FY16<br />

Cost<br />

Current<br />

FY11 ‐ FY16<br />

Cost<br />

Variance Analysis<br />

Project initiated in FY2016<br />

Total 0<br />

212 212<br />