Project Description<br />

WMATA <strong>FY2017</strong> Capital Project Summary<br />

CIP0072 Elevator Rehabilitation<br />

This project rehabilitates the oldest and poorest performing<br />

elevators as necessary to maintain elevator safety,<br />

availability and reliability. The elevators are rehabilitated<br />

with energy saving devices.<br />

Deliverables<br />

Proposed <strong>FY2017</strong> Budget<br />

Appendix A<br />

1) Rehabilitate 15 elevators, planned locations include:<br />

Columbia Heights, Clarendon, Shady Grove, Medical Center,<br />

Archives, New Carrollton, Naylor Rd.,<br />

Franconia Springfield, Brentwood, Deanwood, Brookland,<br />

Pentagon, Southern Ave., Farragut North and Virginia Square<br />

Financial Summary<br />

$10,000,000<br />

$8,000,000<br />

$6,000,000<br />

$4,000,000<br />

$2,000,000<br />

$0<br />

Milestones<br />

1) Ongoing rehabilitation project with milestones completed<br />

as contract requires<br />

FY2016<br />

<strong>FY2017</strong><br />

FY2018<br />

FY2019<br />

FY2020<br />

FY2021<br />

FY2022<br />

Project Financials<br />

FY2016 ‐ FY2011 ‐<br />

Budget (in 000s) FY11‐FY15 FY2016 <strong>FY2017</strong> FY2018 FY2019 FY2020 FY2021 FY2022 FY2022 FY2022<br />

PPersonnel 4,987 2,108 2,219 2,478 2,602 2,733 2,870 3,016 18,026 23,013<br />

NNon‐Personnel 18,600 6,588 4,396 2,220 4,847 4,993 5,142 5,297 33,483 52,083<br />

Total Budget 23,587 8,696 6,615 4,698 7,449 7,725 8,013 8,312 51,509 75,095<br />

Planned Funding Sources<br />

As of 12/16/2015 <strong>FY2017</strong><br />

NPRIIA<br />

6,615<br />

Total 6,615<br />

Original<br />

FY11‐FY16<br />

Cost<br />

Current<br />

FY11 ‐ FY16<br />

Cost<br />

13,067 32,401<br />

Variance Analysis<br />

The project budget has been increased<br />

compared to previous years to include<br />

the recently awarded contract to<br />

rehabilitate 100 elevators over the next<br />

10 years<br />

A-51