Project Description<br />

WMATA <strong>FY2017</strong> Capital Project Summary<br />

CIP0024 Track Rehabilitation<br />

This project rehabilitates the track structure by replacing<br />

deteriorated running rail, crossties, direct fixation fasteners,<br />

third rail insulators and switches annually, in addition to<br />

track stabilization and tamping. Track components require<br />

replacement when, based on industry standards, they<br />

become worn or unserviceable due to deterioration,<br />

excessive wear or defect development. Replacing these<br />

components maintains a state of good repair while<br />

preventing service delays and speed restrictions.<br />

Deliverables<br />

1) Tamping of 40 miles of track to support crosstie renewal<br />

2) Replace 12.5 miles of running rail<br />

3) Replace 20,000 fasteners<br />

4) Replace 16 switches<br />

5) Replace 15,000 crossties<br />

Proposed <strong>FY2017</strong> Budget<br />

Appendix A<br />

Financial Summary<br />

$60,000,000<br />

$55,000,000<br />

$50,000,000<br />

Milestones<br />

1) This is an on‐going program to rehabilitate track by<br />

replacing running rail, fasteners, switches, insulators<br />

and crossties.<br />

$45,000,000<br />

$40,000,000<br />

FY2016<br />

<strong>FY2017</strong><br />

FY2018<br />

FY2019<br />

FY2020<br />

FY2021<br />

FY2022<br />

Project Financials<br />

FY2016 ‐ FY2011 ‐<br />

Budget (in 000s) FY11‐FY15 FY2016 <strong>FY2017</strong> FY2018 FY2019 FY2020 FY2021 FY2022 FY2022 FY2022<br />

PPersonnel 123,700 33,745 28,147 30,447 31,541 32,551 33,496 34,448 224,376 348,076<br />

NNon‐Personnel 99,755 23,148 20,266 19,338 19,865 20,490 21,209 21,593 145,908 245,662<br />

Total Budget 223,454 56,893 48,413 49,786 51,406 53,041 54,705 56,041 370,284 593,739<br />

Planned Funding Sources<br />

As of 12/16/2015<br />

<strong>FY2017</strong><br />

Original<br />

FY11‐FY16<br />

Cost<br />

Current<br />

FY11 ‐ FY16<br />

Cost<br />

Variance Analysis<br />

Expanded scope and increased<br />

investment have resulted in increased<br />

project cost to reduce backlog and work<br />

towards State of Good Repair<br />

NPRIIA<br />

48,413<br />

Total 48,413<br />

213,468 279,892<br />