The Status <strong>of</strong> on going projects is given below:-<br />
1. Teesta HE Project Stage-V (510 MW), Sikkim<br />
Dam concreting and HRT heading, benching, overt lining<br />
and 91.50% invert lining <strong>of</strong> Head Race Tunnel (HRT)<br />
completed. Excavation and lining <strong>of</strong> Desilting Chambers,<br />
erection <strong>of</strong> steel liners in Pressure Shafts/Penstocks are<br />
completed. Civil works <strong>of</strong> <strong>Power</strong> House and TRT have been<br />
completed. Assembly <strong>of</strong> all the 3 generating units<br />
completed. The Project is expected to become fully<br />
operational by March 2008.<br />
2. Parbati HE Project, Stage-II (800 MW), H.P<br />
So far 100% excavation & 55% Dam concreting has been<br />
completed. In HRT excavation <strong>of</strong> 79.50% and concrete<br />
lining <strong>of</strong> 13% length have been completed. During Nov.’06<br />
in HRT face-4, TBM was partly buried due to heavy ingress<br />
<strong>of</strong> silt and water, causing total stoppage <strong>of</strong> work.<br />
Refurbishment <strong>of</strong> TBM has been completed. The HRT,<br />
particularly face-4 is the most critical work <strong>of</strong> the Project.<br />
Excavation <strong>of</strong> both Inclined Pressure Shafts <strong>of</strong> length<br />
1546m each with inclined TBM has been completed. In<br />
<strong>Power</strong>house excavation and 14% concreting had been<br />
completed but in Feb.’07 the back hill slope <strong>of</strong> PH suffered<br />
a slide causing a setback to the works. Slope Stabilization<br />
works are in progress. E&M works have been started.<br />
Supply <strong>of</strong> E&M and HM components is in progress.<br />
3. Sewa HE Project Stage-II (120 MW), J & K<br />
Complete excavation and 80% concreting <strong>of</strong> Dam is over.<br />
In HRT, so far 89.40% excavation has been completed.<br />
Face-7 <strong>of</strong> HRT is the most critical due to very bad geology.<br />
There has been re-routing <strong>of</strong> tunnel twice. Excavation <strong>of</strong><br />
Surge Shaft and <strong>Power</strong>house has been completed and<br />
concreting is in progress. Excavation and concreting <strong>of</strong><br />
Pressure Shafts is in progress. Erection, Alignment &<br />
Boxing up <strong>of</strong> generating units and auxiliaries is in progress.<br />
Design & Engineering work <strong>of</strong> HM and fabrication <strong>of</strong> 1st<br />
stage & 2nd stage embedded parts are in progress. The<br />
project is now expected to be commissioned by June 2009.<br />
4. Subansiri (Lower) HE Project (2000 MW),<br />
Arunachal Pradesh<br />
Major civil works contracts were awarded in December ’03<br />
but start <strong>of</strong> works got delayed due to issues related to forest<br />
clearance by MOEF and payment <strong>of</strong> NPV. The final forest<br />
clearance was accorded on 12th <strong>of</strong> October, 2004 by MOEF.<br />
Diversion Tunnels have been completed and river has been<br />
successfully diverted. Adit to Pressure Shaft completed and<br />
excavation <strong>of</strong> Vertical Pressure shafts are in progress. 57%<br />
<strong>of</strong> Surge Chamber excavation and 97% <strong>of</strong> <strong>Power</strong> House<br />
excavation completed so far. Further work is in progress.<br />
E&M and HM works have also been awarded. The project<br />
is now expected to be commissioned by Jan. 2012.<br />
5. Teesta Low Dam Project, Stage-III (132 MW), West<br />
Bengal.<br />
In Barrage Bays 3 to 7, Intake and PH excavation is over<br />
and concreting is in progress. PH civil works are the most<br />
critical as slides in the PH back hill slope have delayed the<br />
civil as well as E&M works. Supply and erection <strong>of</strong> E&M<br />
and HM components is in progress. Draft Tubes for all the<br />
4 units have been erected. On 27.07.2007 during flash<br />
floods, the C<strong>of</strong>fer dam was overtopped and breached<br />
resulting in flooding <strong>of</strong> the entire work area thus causing a<br />
severe setback to the progress <strong>of</strong> works and delaying the<br />
completion <strong>of</strong> Project. Restoration works are in progress.<br />
The Project is now expected to be completed by<br />
Sept.-Dec.’09.<br />
6. Uri HE Project, Stage-II (240 MW), J&K<br />
Investment approval has been accorded on 01.09.2005 with<br />
commissioning date as Nov. 2009. Major civil works have<br />
been awarded to M/s HCC Ltd. on 21-9-05 but due to major<br />
earthquake that hit the area in Oct.’05, start <strong>of</strong> major civil<br />
works was delayed. River diversion achieved on<br />
21.01.2007. Riverbed excavation started but progress was<br />
affected due to washing away <strong>of</strong> c<strong>of</strong>ferdam. All adits to HRT<br />
and TRT completed, and 89% & 57% excavation <strong>of</strong> heading<br />
completed in HRT & TRT respectively. Excavation <strong>of</strong> MAT<br />
to <strong>Power</strong> House is nearing completion. E&M works<br />
awarded to M/s Alstom on 29th Dec.’06. HM works awarded<br />
to M/s Om Metals-SPML (JV). The project is expected to<br />
be commissioned by August 2010.<br />
7. Chamera HE Project, Stage-III (231MW), H.P<br />
Investment approval has been accorded on 1.9.2005 with<br />
commissioning date as Aug.2010. All the major civil works<br />
awarded to M/S H.C.C Limited. The river has been diverted.<br />
HRT & TRT excavation 54% & 92% completed respectively.<br />
MAT to PH, Pilot tunnel to PH cavern and adit to PS bottom<br />
completed. 93% <strong>Power</strong> House excavation has been<br />
completed. E&M work was awarded to M/s Alstom and HM<br />
works to M/s Om Metals-SPML(JV). The project is expected<br />
to be completed as per schedule by August 2010.<br />
8. Teesta Low Dam Project, Stage-IV (160MW), West<br />
Bengal<br />
Investment approval has been accorded on 30.9.05 with<br />
commissioning date as Sept.2009. Civil works package was<br />
awarded to M/S HCC Ltd. with completion by Aug’09.<br />
Formal forest clearance has been received on 30/3/06 and<br />
forestland was handed over to NHPC on 20.04.06. The 1st<br />
Stage diversion was achieved on 30.1.07. So far major part<br />
<strong>of</strong> excavation for Dam component & Energy Dissipaters,<br />
PH, Cellular wall and TRC has been completed. Cellular<br />
Wall and <strong>Power</strong>house works are critical. HM and E&M<br />
packages have been awarded to M/s BHEL and M/s Om<br />
Metals. During heavy floods on 17.7.2007 the C<strong>of</strong>fer Dam<br />
was breached and whole Cellular Wall, Dam & <strong>Power</strong>house<br />
area got inundated. Restoration Work got affected due to<br />
recurrence <strong>of</strong> flash floods on 27th July 2007. Restoration<br />
101