Sl. Schemes Progress upto Target upto 3/08 Remarks<br />

no. 11/07<br />

6. 3rd Ckt. Between MHS & 85% 100% Work under progress.<br />

Kalyaneswari S/S<br />

7. 132 kV CTPS-BIADA Line 20% 100% Work under progress.<br />

8. 132/33 kV Jamuria S/S 90% 100% Work under progress.<br />

9. Belmuri S/S-50MVA Tr. & NA NA Transformer commissioned<br />

feeder bay on 03.05.07.<br />

10. 132 kV Infrastructure at 60% 80% Work under progress.<br />

Barjora S/Stn.<br />

11. Reconductoring <strong>of</strong> 132 kV 98% 100% Reconductoring work<br />

Bokaro-Konar-Barhi Line pending E/W completed<br />

in 6/07.<br />

12. Reconductoring <strong>of</strong> 132 kV NA NA Line charged after<br />

Putki-Nimiaghat reconductoring in 5/07.<br />

13. Giridih S/S-2 No. 80 MVA 100% 100% 1st Transformer<br />

Tr. & associated work commissioned on 21.9.2006<br />

& 2nd Transformer<br />

commissioned on 25.5.2007<br />

14. Retr<strong>of</strong>itting <strong>of</strong> Numerical 35% 70% Work under progress.<br />

relays in various substations<br />

15. 6 No. 220 kV Bays at 7% 60% Order placed on 15.6.07.<br />

Mejia, Kalyaneswari &<br />

Ramgarh S/Stn.<br />

16. Reconductoring <strong>of</strong> 2 No. 3% 20% Order placed on 03.8.07.<br />

CTPS-Putki D/C line<br />

Projects initiated<br />

1. 220 kV Dhanbad S/Stn. 5% 15% Order placed on 21.9.07.<br />

LILO <strong>of</strong> 220kV CTPS-Kly<br />

at Dhanbad<br />

2. 220 kV Gola S/Stn. NA 5% Subject to availability <strong>of</strong> land<br />

3. 220 kV Giridih S/Stn. NA 5% Subject to availability <strong>of</strong> land<br />

4. 220 kV Uluberia S/Stn. NA 5% Subject to availability <strong>of</strong> land<br />

5. Retr<strong>of</strong>itting <strong>of</strong> 31 No. NA 50% Procurement <strong>of</strong> CB<br />

breakers at various S/Stns. under process.<br />

6. System Energy Management NA 10% Order to be placed in 12/07.<br />

7. 220 kV Dhanbad-Giridih Line NA 5% Tendering under process.<br />

8. 220 kV Koderma-Giridih Line NA 5% Tendering under process.<br />

9. 400 kV Lines -1304 ckm. NA 5% Tendering under process.<br />

161