154<br />

In Jan' 07, THDC has engaged International Consultants<br />

i.e. COYNE –ET – BELLEIR (France) for the consultancy<br />

services for Tehri PSP.<br />

Global bids have been invited for the EPC package under<br />

ICB in Aug-07. Meanwhile, works <strong>of</strong> Approach Adits, have<br />

been taken up. The Project is scheduled to be<br />

commissioned by Dec’ 11.<br />

PROJECTS AWAITING INVESTMENT APPROVAL<br />

Vishnugad Pipalkoti HEP (444 MW):<br />

The Project envisages construction <strong>of</strong> 65 m high Gated<br />

Diversion Dam, on the river Alaknanda near village Helong<br />

in Chamoli Distt., Uttarakhand and an underground <strong>Power</strong><br />

House with installed capacity <strong>of</strong> 444 MW (4 x 111 MW).<br />

The Implementation Agreement for the Project was signed<br />

with the Govt. <strong>of</strong> Uttarakhand in June’ 06. Techno Economic<br />

Clearance to the Project was accorded by CEA during Sept.’<br />

06. <strong>Power</strong> Purchase Agreements (PPAs) have already been<br />

signed for the full rated capacity <strong>of</strong> the Project with five<br />

States and the commercial arrangements firmed up for <strong>of</strong>ftake<br />

<strong>of</strong> entire power from the Project. Consultations with<br />

other States <strong>of</strong> Northern Region are under progress to sign<br />

agreements for their share. The Public Investment Board<br />

(PIB), during Feb’ 07 has recommended the Project for the<br />

consideration <strong>of</strong> CCEA. Environmental Clearance to the<br />

Project has also been accorded by the <strong>Ministry</strong> <strong>of</strong><br />

Environment & Forests in August’ 07 and the Project has<br />

been posed for Investment sanction.<br />

A view <strong>of</strong> New Tehri Township - THDC<br />

PROJECTS UNDER FR/DPR PREPARATION<br />

Govt. <strong>of</strong> Uttarakhand had allotted six Projects to THDC,<br />

with a total installed capacity <strong>of</strong> 695 MW, for which<br />

Implementation Agreements were signed in Nov’ 05. Of<br />

the six Projects, Bokang Bailing (330 MW) falls in Askot<br />

Musk Deer Sanctuary, while Karmoli (140MW) and<br />

Jadhganga (50 MW) H.E. Projects fall under the “Gangotri<br />

National Park”. Prior permission <strong>of</strong> Hon’ble Supreme Court<br />

is required for taking up activities on the three Projects.<br />

Necessary IA has been filed by THDC in the Hon’ble<br />

Supreme Court seeking clearance for taking up work on<br />

the Bokang Bailing HEP while the matter relating to Karmoli<br />

and Jadhganga Projects is taken up with the State<br />

authorities. Work <strong>of</strong> Survey & Investigation and preparation<br />

<strong>of</strong> Feasibility Report (FR) is under progress on Malari<br />

Jhelam (60 MW) and Jhelam Tamak (55 MW). The FR <strong>of</strong><br />

Gohana Tal (60MW) has however been kept in abeyance<br />

pending decision <strong>of</strong> Govt. <strong>of</strong> Uttarakhand on the optimum<br />

utilization <strong>of</strong> the head available for the Project.<br />

ENGINEERING CONSULTANCY<br />

THDC is engaged in the engineering consultancy work for<br />

stabilization <strong>of</strong> Varunavat Parvat in Uttarkashi entrusted by<br />

Government <strong>of</strong> Uttarakhand. The work involves providing<br />

the complete engineering solution to the major hill<br />

stabilization problem and also supervising the execution<br />

works at site. The work is at an advance stage <strong>of</strong><br />

completion.