04.08.2013 Views

MoP - Ministry of Power

MoP - Ministry of Power

MoP - Ministry of Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

102<br />

works are in progress. Works have been restarted at some<br />

sites. The project is expected to be commissioned by<br />

August 2010.<br />

9. Parbati HE Project, Stage-III (520MW), H.P<br />

Investment approval has been accorded on 9.11.2005 with<br />

commissioning date as Nov.2010. Major Civil works (2 lots)<br />

were awarded on 15.12.2005 to M/s Patel-L&T consortium<br />

and M/s Jager-Gammon JV. The river has been diverted.<br />

70% Excavation <strong>of</strong> Dam and 14% <strong>of</strong> HRT excavation<br />

completed. Adits to Desilting Chambers, Pressure Shaft,<br />

GOC, TRT and Surge Shaft bottom, GIS & Transformer<br />

caverns have been completed. In TRT, 47% excavation<br />

has been completed. E&M work has been awarded to M/s<br />

BHEL. HM works has been awarded to M/s Om Metals-<br />

SPML(JV). The project is expected to be completed as per<br />

schedule by November 2010.<br />

10. Nimoo Bazgo HE Project (45MW), J&K<br />

Investment approval has been accorded on 24.08.06 for<br />

completion <strong>of</strong> the project in 48 months i.e August 2010.<br />

Major civil works awarded to M/s H.C.C Ltd. on 23.9.06.<br />

E&M works were awarded to M/s BHEL on 12.06.07. The<br />

works are progressing satisfactorily in spite <strong>of</strong> difficult<br />

condition and river has been diverted on 22.11.07. The<br />

project is expected to be completed as per schedule.<br />

11. Chutak HE Project (44MW), J&K<br />

Investment approval has been accorded on 24.08.06 for<br />

completion <strong>of</strong> the project in 54 months i.e Feb. 2011. Major<br />

civil works have been awarded to M/s H.C.C Ltd..<br />

Excavation <strong>of</strong> Adit-1 & 3 is completed and HRT excavation<br />

started. PH ventilation tunnel excavation has been<br />

completed. E&M works have been awarded to M/s BHEL<br />

480 MW URI <strong>Power</strong> Station (J&K) - Aerial view <strong>of</strong> Barrage<br />

on 16.08.2007.The works are progressing satisfactorily in<br />

spite <strong>of</strong> difficult condition and river has been diverted on<br />

22.11.07. The project is expected to be completed as per<br />

schedule.<br />

12. Kishanganga HE Project (330 MW), J&K<br />

Investment approval has been accorded on 20.07.2007 for<br />

completion <strong>of</strong> the Project in seven years from the date <strong>of</strong><br />

sanction, i.e. by July 2014. The lowest price bid for turnkey<br />

contract package was received for Rs.2961 crores against<br />

estimated cost <strong>of</strong> Rs. 1336 crores (approx.). The case is<br />

under examination for further course <strong>of</strong> action<br />

13. Omkareshwar HE Project (520 MW), Madhya<br />

Pradesh<br />

Investment approval has been accorded on 29.05.2003 for<br />

completion by Feb.’08 and work on turnkey basis was<br />

awarded to M/s Jai Prakash – Voith Siemens Consortium,<br />

New Delhi on 09.06.2003. The Project has been completed<br />

and all 8 units have started commercial generation from<br />

15.11.2007 ahead <strong>of</strong> schedule. However due to ban by court<br />

on charging <strong>of</strong> reservoir above EL 189 m upto EL 196.60<br />

m as R&R work has not been completed by the State Govt.,<br />

full benefits <strong>of</strong> generation are not available.<br />

PROPOSED XI TH PLAN CAPACITY ADDITION<br />

PROGRAMME<br />

NHPC has proposed to commission 12 projects to add 5322<br />

MW capacity during XIth plan including one project <strong>of</strong> 520 MW<br />

in Joint Venture with Government <strong>of</strong> Madhya Pradesh has<br />

already been commissioned. Two projects with total capacity<br />

<strong>of</strong> 89 MW are included in the capacity addition programme<br />

under best effort category.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!