Financial Performance<br />
THDC has reported a Net Pr<strong>of</strong>it <strong>of</strong> Rs. 1309.13 Million in<br />
the first year <strong>of</strong> commercial operations. The total sale <strong>of</strong><br />
energy during the year was Rs. 4441.59 Million.<br />
Operational Performance<br />
During the year 2006-07, three units <strong>of</strong> the Tehri <strong>Power</strong><br />
Station <strong>of</strong> 250 MW each were put under commercial<br />
operation while the fourth unit <strong>of</strong> 250 MW has started<br />
commercial generation in July’ 07. The Irrigation and<br />
Drinking water benefits from the Project have also started<br />
to flow to Uttar Pradesh and Delhi.<br />
Tehri <strong>Power</strong> Station generated 891 MUs <strong>of</strong> energy during<br />
2006-07 while the target for 2007-08 is 2649 MU. During<br />
2007-08, 1776 MU <strong>of</strong> energy has been generated from the<br />
Tehri <strong>Power</strong> Station till Nov.’07. During 2006-07, the<br />
Capacity Index achieved by the Plant was 86%. For the<br />
year 2007-08, Tehri <strong>Power</strong> Station is operating at a Capacity<br />
Index <strong>of</strong> above 90%.<br />
Commercial Performance<br />
During financial year 2006-07, Revenue <strong>of</strong> Rs. 258.37 Cr.<br />
has been realized from the beneficiaries from the sale <strong>of</strong><br />
<strong>Power</strong> from Tehri <strong>Power</strong> Station against the billing <strong>of</strong> Rs.<br />
262.89 Cr. as per Interim order <strong>of</strong> CERC.<br />
Further, during the current fiscal 2007-08, revenue <strong>of</strong> Rs.<br />
501.79 Cr. has been realized from the beneficiaries from<br />
the sale <strong>of</strong> electrical energy generated between 01.04.2007<br />
& 31.10.2007 against the billing <strong>of</strong> Rs. 550.15 Cr.<br />
A view <strong>of</strong> Machine Hall- THDC<br />
PROGRESS OF ON GOING PROJECTS<br />
Koteshwar HEP (400 MW):<br />
Koteshwar Project comprises a 97.5 m high concrete Dam<br />
and Surface <strong>Power</strong> House, housing 4 units <strong>of</strong> 100 MW<br />
each and is located around 22 Km downstream <strong>of</strong> Tehri<br />
Dam. Koteshwar Project is a run-<strong>of</strong>f-river scheme with<br />
minimum diurnal storage. The Project had encountered<br />
some delay in the evacuation <strong>of</strong> the affected villages. With<br />
the evacuation <strong>of</strong> all villages by Mar-07, the progress <strong>of</strong><br />
works has gained momentum. After completion <strong>of</strong> the<br />
excavation work in the major areas, concreting work has<br />
been taken. The Project is scheduled for commissioning<br />
by December’10.<br />
Tehri PSP (1000 MW):<br />
Government approval for the 1000 MW Tehri Pumped<br />
Storage Plant, the first Central Sector PSS, was another<br />
major landmark for THDC during the year 2006-07. The<br />
Tehri PSP involves the arrangement <strong>of</strong> banking<br />
transaction <strong>of</strong> power, which has been adopted for the<br />
first time in the development <strong>of</strong> PSS in the Country. Under<br />
this arrangement, the beneficiaries, who supply input power<br />
for the pumping operation <strong>of</strong> the Tehri PSP, would receive<br />
power in return, after adjusting for losses, during peak<br />
hours, when the demand is maximum. This pioneering<br />
arrangement has set a model for development <strong>of</strong> the large<br />
potential <strong>of</strong> over 94,000 MW in PSS in the Country.<br />
The essential works <strong>of</strong> Tehri PSP approved along with Tehri<br />
Stage-I have already been completed. Major works have<br />
been planned to be executed through an EPC package.<br />