Transmission projects continue to be accorded a high<br />

priority in the context <strong>of</strong> the need to evacuate power from<br />

the generating stations to the load centers, system<br />

strengthening and creation <strong>of</strong> National Grid. The<br />

CHAPTER - 7<br />

TRANSMISSION<br />

construction targets for the year 2007-08 and achievement<br />

up to November, 2007 <strong>of</strong> Central Sector Transmission<br />

projects including Joint Venture projects <strong>of</strong> POWERGRID<br />

are summarized below:<br />

Works Programme for Achievement % <strong>of</strong><br />

the year 2007-08 upto Nov. 2007 Achievement<br />

765 kV lines 160 Ckm. 220 Ckm. 137.50<br />

400 kV lines 4894 Ckm. 3934 Ckm. 80.38<br />

220 kV lines 224 Ckm. 275 Ckm. 122.77<br />

765 kV Sub-Stations 2169 MVA 1500 MVA 69.16<br />

400 kV Sub-Stations 8940 MVA 3965 MVA 44.35<br />

220 kV Sub-Stations 400 MVA 100 MVA 25.00<br />

CENTRAL SECTOR TRANSMISSION<br />

<strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> has planned to establish the requisite<br />

transmission capacity in the Central Sector to match the<br />

generation capacity addition and encourage inter-state/inter-<br />

regional exchange <strong>of</strong> power to mitigate the situation <strong>of</strong><br />

surplus /deficit <strong>of</strong> power in various regions. Transmission<br />

lines and sub-stations completed during the year 2007-08<br />

(up to Nov, 07) are shown in the following table:<br />

S. No. Name <strong>of</strong> the transmission line/Sub-station No. <strong>of</strong> ckt Voltage kV<br />

1. TRANSMISSION LINES<br />

i) Talchar-Kolar (Aug.) 500 MW Bipole ± 500 HVDC<br />

ii) Sipat - Seoni Line1 S/C 765<br />

iii) Balia - Lucknow D/C 400<br />

iv) Maithon - Ranchi D/C 400<br />

v) Line from Singrauli to a point 2.3 Km near existing<br />

Vindhyachal - Kanpur Line.<br />

D/C 400<br />

vi) Gooty - Raichur D/C 400<br />

vii) Vindhyachal - Korba S/C 400<br />

viii) Lucknow - Bareilly D/C 400<br />

ix) LILO <strong>of</strong> Bareilly - Mandaula at Bareilly 2xD/C 400<br />

x) Satna - Bina Ckt-II S/C on D/C 400<br />

xi) LILO <strong>of</strong> Lucknow - Moradabad at Bareilly D/C 400<br />

xii) Satna - Bina Ckt-I D/C 400