SECTION 01001 HVAC COORDINATION COMMISSIONING AND CLOSE-OUT<br />

1.0 HVAC PROJECT COORDINATION MEETINGS:<br />

The General <strong>and</strong>/or Prime Contractor shall send his Mechanical Foreman to all Tuesday morning project<br />

coordination meetings. These meetings shall be held in the Civil Engineering Building (B.4705) every<br />

Tuesday morning at 7:30 am unless notified otherwise. The contractors’ representative shall be the point of<br />

contact for the project <strong>and</strong> the most familiar with the project progress <strong>and</strong> details. The purpose of these<br />

meetings shall be for project update <strong>and</strong> coordination purposes.<br />

2.0 PROJECT CLOSE-OUT SEQUENCE:<br />

The General Contractor <strong>and</strong> Mechanical Contractor are required to coordinate the following sequence with<br />

the CSC STM, Designer/Engineer <strong>and</strong> CSC CEOM shop supervisor one month prior to the beginning of the<br />

Certified Factory Start-Up for all equipment. All coordination requests must be submitted in writing or e-<br />

mail to the STM. The Contractor shall submit proof of Factory Technician Start-Up Certification <strong>and</strong><br />

Factory Start-Up Report for approval in the submittal process. All of the following procedures are<br />

sequential <strong>and</strong> must therefore be coordinated <strong>and</strong> executed in sequential order. The Contractor will be<br />

allowed to proceed to each sequential item based on successful completion of each item as approved <strong>and</strong><br />

directed by the STM.<br />

1. Controls Commissioning with Commissioning Reports for all Devices: The Contractor shall not<br />

proceed to item #2 until all controls commissioning reports for all devices are submitted to the STM <strong>and</strong><br />

approved. Controls commissioning reports shall be submitted upon the immediate completion of controls<br />

commissioning so as not to delay the project. The Contractor shall begin delivery of all Close-Out materials<br />

at this point (see item #7).<br />

2. Operational Test: After completion of installation, all mechanical systems shall be started <strong>and</strong> operated<br />

to prove proper functioning of each item of equipment. All operating test shall be scheduled with the STM<br />

<strong>and</strong> performed to the satisfaction of the STM. The contractor shall coordinate the controls contractor to be<br />

present. Should any element or individual piece of equipment not perform properly, the Contractor shall<br />

make all required corrections <strong>and</strong> repeat the operational test for the equipment in question <strong>and</strong>/or any other<br />

related equipment that must operate in unison to the satisfaction of the STM before proceeding to item #3.<br />

3. Certified Factory Start-up with Certified Factory Start-up Report: After equipment installation <strong>and</strong><br />

operational test are completed; the Contractor shall provide the services of a manufacturer certified field<br />

representative for starting the unit <strong>and</strong> training for the CSC CEOM operator(s) <strong>and</strong> or technician(s) at no<br />

additional costs. Training can occur sequential to Certified Factory Start-Up if successful <strong>and</strong> the STM is<br />

provided the Certified Factory Start-Up Report immediately upon completion, approved, <strong>and</strong> Certified<br />

Factory Training has been previously coordinated. Uncertified vendor field representatives are not allowed.<br />

Factory certified vendor field representatives are only allowed if they are approved during the submittal<br />

process. The contractor shall coordinate the controls contractor to be present. The Contractor shall present<br />

CSC STM with all required copies of the O&M manuals upon completion of Factory Start-Up <strong>and</strong> prior to<br />

Training.<br />

4. Test <strong>and</strong> Balance: The contractor shall provide complete Test & Balance service as dictated by the<br />

specifications. Any deviations from the Test & Balance specification shall be requested in writing to the<br />

CSC STM <strong>and</strong> approved by the Designer/Engineer. The Contractor shall request in writing all pertinent<br />

information required for Test & Balance if additional or any information is needed. The Test & Balance<br />

Report shall be presented to the Designer/Engineer within 48 Hours for approval by the Designer/Engineer.<br />

The Designer/Engineer shall have 1 week to review upon receipt thereof. Additional details of the Test &<br />

Balance requirements are presented specifically in the Test & Balance section of the specifications.<br />

SECTION 01001<br />

Page 1 of 4