4. Wet floor tiles with amended water during removal to minimize fiber release<br />

during removal. Use amended water sparingly <strong>and</strong> apply with a sponge, cloth<br />

or mop to eliminate st<strong>and</strong>ing water <strong>and</strong> to prevent water from traveling to other<br />

areas. If approved in advance by the Contracting Officer, a damp towel may<br />

be placed over tiles during removal as an alternate to a direct application of<br />

amended water.<br />

5. Remove individual floor tiles by wedging a scraper under one edge of the tile<br />

<strong>and</strong> exerting a twisting, prying force as it is moved under the tile until the tile<br />

releases from the substrate. Avoid breaking floor tiles. If tiles do not release<br />

easily, a mallet or hammer may be used to strike the scraper <strong>and</strong> force it under<br />

the floor tile; hot air blowers may be used to heat the tile <strong>and</strong> soften the<br />

adhesive. Place tiles in asbestos disposal bags immediately after removal<br />

from substrate.<br />

6. Scrape up remaining mastic <strong>and</strong> adhesives <strong>and</strong> deposit scrapings in disposal<br />

bags as small areas of floor are cleared of tile.<br />

7. Clean floor of all visible mastic residue by wet mopping with approved solvent.<br />

3.3 EQUIPMENT REMOVAL PROCEDURE<br />

A. Clean external surfaces of contaminated containers <strong>and</strong> equipment thoroughly by<br />

wet sponging or HEPA vacuum before moving such items into the equipment<br />

decontamination enclosure system washroom for final cleaning <strong>and</strong> removal to<br />

uncontaminated areas. Ensure that personnel do not leave work areas through the<br />

equipment decontamination enclosure system.<br />

3.4 FIRST CLEANING – GENERAL<br />

A. First Cleaning: Carry out a first class cleaning of all surfaces of the work area<br />

including items of remaining sheeting, tools, scaffolding <strong>and</strong>/or staging by use of<br />

damp cleaning <strong>and</strong> mopping, <strong>and</strong>/or a High Efficiency Particulate Absolute (HEPA)<br />

filtered vacuum. (Note: A HEPA vacuum will fail if used with wet material.) Do not<br />

perform dry dusting or dry sweeping. Use each surface of a cleaning cloth one<br />

time only <strong>and</strong> then dispose of as contaminated waste. Continue this cleaning until<br />

there is no visible debris from removed materials or residue on plastic sheeting or<br />

other surfaces.<br />

B. Remove all filters in air h<strong>and</strong>ling system(s) <strong>and</strong> dispose of as asbestos containing<br />

waste.<br />

C. Wait 24 hours to allow negative air machines to clean air of airborne asbestos<br />

fibers. Use oscillating fans as necessary to assure circulation of air in all parts of<br />

work areas during this period. Maintain negative pressure system in operation for<br />

the entire 24 hour period.<br />

D. Encapsulation of Substrate: Perform encapsulation of substrate where required at<br />

this time. Maintain negative air system in operation during encapsulation work.<br />

Encapsulant shall be spray applied with coverages as recommended by the<br />

manufacturer. Encapsulant shall be tinted a contrasting color to the substrate, to<br />

facilitate verification of coverage.<br />

MAHG121038 02 11 50 - 11 ASBESTOS REMOVAL