SECTION 01779<br />

TESTING AND ACCEPTANCE<br />

1.0 GENERAL<br />

1.1 REQUIREMENTS INCLUDED<br />

A. Administrative provisions for Substantial Completion <strong>and</strong> for final acceptance.<br />

B. Submittal of Operation <strong>and</strong> Maintenance manuals.<br />

C. Submittal of Record Drawings.<br />

1.2 RELATED REQUIREMENTS<br />

A. Section 01782 - Operation <strong>and</strong> Maintenance Data.<br />

1.3 TESTING ON LOCAL POWER<br />

A. When the CONTRACTOR considers the work complete, he shall notify the Contracting Officer in<br />

writing that the project is ready for testing <strong>and</strong> acceptance.<br />

B. The Contracting Officer shall notify the Contractor of the date on which the testing shall begin.<br />

C. The testing shall consist of a seven (7) day continuous run period in which the well <strong>and</strong> all related<br />

mechanical <strong>and</strong> electrical systems will operate in automatic mode off of the local power grid.<br />

D. In the event the system goes off line for any reason to include equipment failure, adjustments or has to<br />

be run in the manual mode the test period shall be stopped. When repairs have been made <strong>and</strong> the<br />

system is restarted in the automatic mode the test will commence at the first hour <strong>and</strong> proceed for a<br />

seven (7) day period.<br />

E. It is the Contractors responsibility to continue the testing until such time as the system operates in the<br />

automatic mode for a full seven (7) day period without interruption.<br />

1.4 TESTING ON EMERGENCY POWER<br />

Upon completion of the seven (7) day Local Power test the Contractor shall operate the system on the<br />

emergency power for five (5) cycles. Each cycle shall consist of interrupting the local power, which will activate<br />

the emergency generator. The system then shall be operated on emergency power for a period of two(2) hours.<br />

Upon completion of each two (2) hour run on emergency power the system will be returned to local power <strong>and</strong><br />

allowed to run on local power for one hour before starting the next cycle on emergency power. In the event the<br />

system goes off line while on emergency power for any reason to include equipment failure, adjustments or has<br />

to be run in the manual mode the test period shall be stopped. When repairs have been made <strong>and</strong> the system is<br />

restarted on emergency power the test will commence at the first hour <strong>and</strong> proceed for five (5) full cycles.<br />

1.5 ACCEPTANCE BY THE CONTRACTING OFFICER<br />

The Contracting Officer upon completion of both the local <strong>and</strong> emergency power test shall notify the Contractor<br />

in writing of the acceptance of the project. In the event the Contractor fails to complete the required testing the<br />

Contracting Officer is under no obligation to accept the work in place <strong>and</strong> it becomes the full responsibility of<br />

the Contractor to make any <strong>and</strong> all modifications, repairs or replacement of equipment at his sole expense until<br />

such time as the system can pass the full testing procedures.<br />

1.6 APPLICATION FOR FINAL PAYMENT<br />

Prior to application for final payment, the CONTRACTOR receive in writing a letter of acceptance from the<br />

Contracting Officer.<br />

END OF SECTION<br />

SECTION 01779<br />

Page 1 of 1