3.5 SECOND CLEANING – GENERAL<br />

A. Second Cleaning: Carry out a second cleaning of all surfaces in the work area in<br />

the same manner as the first cleaning.<br />

B. Immediately following the second cleaning, the Testing Laboratory shall perform<br />

the Final Air Clearance Testing described in Section 4.3, below.<br />

C. After area passes Final Clearance Test, remove wall sheeting <strong>and</strong> floor sheeting.<br />

3.6 THIRD CLEANING – GENERAL<br />

A. Carry out a third cleaning of all surfaces in the work area in the same manner as<br />

the first cleaning immediately after removal of primary plastic. This cleaning is now<br />

being applied to existing room surfaces.<br />

B. Wait 24 hours to allow negative air machines to clean air of airborne asbestos<br />

fibers. Use oscillating fans as necessary to assure circulation of air in all parts of<br />

work areas during this period. Maintain negative pressure system in operation for<br />

the entire 24 hour period.<br />

3.7 FINAL CLEANING – GENERAL<br />

A. Carry out a final cleaning of all surfaces in the work area in the same manner as<br />

the previous cleaning.<br />

B. Wait 24 hours to allow negative air machines to clean air of airborne asbestos<br />

fibers. Use oscillating fans as necessary to assure circulation of air in all parts of<br />

work areas during this period. Maintain negative pressure system in operation for<br />

the entire 24 hour period.<br />

3.8 VISUAL INSPECTION<br />

A. After 24 hours perform a complete visual inspection of the entire work area<br />

including decontamination unit, all plastic sheeting, seals over ventilation openings,<br />

doorways, windows, <strong>and</strong> other openings; look for debris from any sources, residue<br />

on surfaces, dust or other matter. If any such debris, residue, dust or other matter<br />

is found repeat final cleaning <strong>and</strong> continue decontamination procedure from that<br />

point. When the area is visually clean, complete the certification at the end of this<br />

section. Visual inspection is not complete until confirmed in writing, on the<br />

certification, by Project Superintendent.<br />

3.9 DISPOSAL – GENERAL<br />

A. Disposal of asbestos-containing materials <strong>and</strong> asbestos-contaminated waste shall<br />

be the responsibility of the Contractor. As the work progresses, <strong>and</strong> to prevent<br />

exceeding available storage capacity on site, remove sealed <strong>and</strong> labeled<br />

containers of asbestos waste <strong>and</strong> dispose of such containers at an authorized<br />

disposal site in accordance with the requirements of disposal authority. Submit<br />

documentation regarding disposal to Government.<br />

MAHG121038 02 11 50 - 12 ASBESTOS REMOVAL