C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 258<br />

6) Excavation to the required lines, curves, section and grades.<br />

7) Conveying the excavated materials including all lifts and lead<br />

upto 50 m. (about 164’), spreading in layers or stacking as<br />

directed and disposing off unwanted materials.<br />

8) All labour, materials and use of equipment and tolls required<br />

for completing the item satisfactorily.<br />

9) Compensation on account of damages, accidents or use of<br />

private lands royalty, etc.<br />

3.13 MODE OF MEASUREMENT & PAYMENT:<br />

The contract rate shall be for a unit of one cubic metre for the strata<br />

mentioned in the wording of the items of excavation acceptably<br />

completed, limited to the dimensions shown on the plans or as<br />

directed by the Engineer. Excavation shall be measured in its original<br />

position by the taking cross-sections before the work start and after it<br />

is entirely completed. The quantity shall be worked out by the<br />

Average End Area method. The individual dimensions and areas of<br />

the cutting shall be measured correct upto two places of decimals of<br />

a metre and square metre respectively and the quantity worked out<br />

correct up to two places of decimals of a cubic metre.<br />

When the classification of the strata changes, the contractor shall<br />

bring this to the notice of the Engineer who will then verify and if<br />

necessary take levels for the changed strata for purpose of<br />

measurement.<br />

The engineer at his option may direct dead-men to be left at such<br />

intervals as he may indicate for purpose of measuring the depths<br />

and other dimensions either for initial measurements or for

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!