<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 360<br />

ii) After 28 days of curing, test specimen will be fitted in a machine<br />

such that the specimen can be placed in water under pressure<br />

upto 7 bars. The typical machine shall be similar to one shown<br />

in Appendix 1700/II of MORT&H 4th revision, 2001 reprint.<br />

iii) At first a pressure of one bar is applied for 48 hours, followed by<br />

3 bars for 24 hours and 7 bars for next 24 hours.<br />

iv) After the passage of the above period, the specimen is taken out<br />

and split in the middle by compression applied on two round<br />

bars on opposite sides above and below.<br />

v) The water penetration in the broken core is measured with scale<br />

and the depth of penetration assessed in mm (max permissible<br />

limit 25mm)<br />

5.9.0 ACCEPTABILITY CRITERIA<br />

5.9.1 Concrete Cubes<br />

5.9.1.1 The strength requirement of any <strong>particular</strong> grade of concrete will be<br />

considered satisfactory if the 28 day’s compressive strengths of<br />

individual sets (each set consists of 3 cubes) and of individual cubes<br />

satisfy the requirements as per IS: 456-2000, Clause No.16:<br />

Acceptance Criteria.<br />

5.9.1.2 Whenever a mix is redesigned due to a change in the quality of<br />

aggregates or cement or plasticiser or for any other reason, it shall be<br />

considered as a new mix and initially subject to the acceptability<br />

criteria.<br />

5.9.1.3 If the concrete produced at site does not satisfy the above strength<br />

requirements, the Engineer will reserve the right to require the<br />

Contractor to improve the methods of batching, the quality of the<br />

ingredients and redesign the mix with increased cement content if<br />

necessary. The Contractor shall not be entitled to claim any extra cost