<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 508<br />

material which shall give a good finish to the concrete surface<br />

finish. For work which are of respective nature, such as column<br />

footings, pedestals for pipe pedestal footing. The formwork shall<br />

be fabricated out of steel plates and structurals to obtain uniform<br />

finish throughout the work. In call cases the form work shall be<br />

inspected and approved by the Engineer, before any concreting is<br />

started. The contractors shall however, be solely responsible for<br />

the proper design, adequacy and stability of the formwork. If at<br />

any time in the opinion of the Engineer, the formwork provided is<br />

not considered sufficiently rigid and/or is defective the contractors<br />

shall improve or strengthen the same in such a manner as the<br />

Engineer may direct.<br />

d) Removal of form work<br />

In no circumstances shall forms be stuck off until the concrete<br />

reaches adequate strength as required or without obtaining<br />

permission of the Engineer. All form work shall be removed<br />

without such shock or vibration as would damage to concrete.<br />

Before the soffit and the strats are removed the concrete surface<br />

shall be exposed where necessary in order to ascertain that the<br />

concrete has hardened sufficiently. The responsibility for the<br />

removal of the form work whether whole or part, shall rest<br />

entirely with the contractors who must nevertheless be guided by<br />

the opinion of the Engineer in this regard. The work of striking<br />

and the removal of form work shall be conducted in the presence<br />

of the Engineer and under personal supervision of a competent<br />

foremen in the employment of the contractor.