<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 438<br />

these wage gases, such work and also that of removing such stop or<br />

plug shall be done by the <strong>CIDCO</strong> staff trained for such work and under<br />

the supervision of a responsible officer as may be directed by the<br />

Engineer and the cost of such work will be borne by the Contractor.<br />

i) Protection of Work from Sun<br />

All cement work, pointing plastering and concrete work shall be shaded<br />

from the sun, and surface kept mostaned until, in the opinion of the<br />

Engineer it is thoroughly set.<br />

Definition of Incomplete Work<br />

A line or stretch of pipe sewer (including the excavation thereof and all<br />

other accessories thereto) will be considered incomplete unless entirely<br />

laid jointed and fully tested, encased wherever required the trenches<br />

filled and consolidated, and the manhole at each and completely<br />

finished with floors, channels cover and all other detail. A manhole will<br />

be considered incomplete unless it is completely finished as above, and<br />

at least one of the lines of pipe sewer to which it belongs or it attached,<br />

is complete as described above.<br />

The Contractors shall have no claim for incomplete work and no<br />

incomplete work will be measured up for payment to the Contractors.<br />

22.2 MEASUREMENT FOR TRANSPORT OF RUBBLES<br />

Serviceable rock will be permitted to be used for refilling trenches.<br />

The measurement for the items of transport of rubble to specified<br />

distance will be either by lorry measurements or depot measurement as<br />

directed without deducting anything in quantities in excess of the<br />

calculated surplus material to be removed as per excavation item.