<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 265<br />

Proper sequence of all component operation shall be maintained to<br />

give individual progress.<br />

To all for subsequent settlement, the finished level or of the<br />

embankment may be kept higher than the specified level by 1 cm. for<br />

each metre of the height of the bank and this, if provided, will be paid<br />

for.<br />

The hauling equipment, animals, labour etc., shall be made to go<br />

over the bank as far as possible, to get the initial compaction. Care<br />

shall be taken for getting good compaction behind abutments returns<br />

and wings walls, etc.<br />

Bank-work in areas not accessible to rollers such as those adjoining<br />

bridges, culverts and other work, shall be carried out independently of<br />

the main embankment and shall be have the layers placed in 10 cm.<br />

to 15 cm. (about 4" to 6") height and each layer shall be moistened<br />

and thoroughly compacted with mechanical or manual tampers.<br />

Embankment shall be brought up simultaneously in equal layers on<br />

each side and compacted carefully to avoid unequal pressure etc.<br />

4.7 PROTECTION:<br />

Proper care shall be taken to ensure that the method of operation and<br />

compaction of the bank-word does not cause damage or undue strain<br />

to any structural element. Embankment over and around bridges or<br />

culverts shall be of approved materials and carefully placed and<br />

compacted. The contractor shall take all precautions necessary for the<br />

protection of the bank-work by diversion of streams, local surface<br />

drainage, rain water etc. likely to damage the bank. Any damage to<br />

the bank-work due to no protection or inadequate protection shall be<br />

made good by the contractor at his own cost. Conveyance of materials<br />

shall not cause obstruction or nuisance to the nearby property owners<br />

and traffic.