<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 465<br />

no measurements taken in water. The pumping shall be continued<br />

so long after execution of any portion of work and repeated so after<br />

as the Engineer may consider as necessary. The pumps and power<br />

applied must be such as the Engineer may determine to be sufficient<br />

at any <strong>particular</strong> time, so he may himself supply pumps and power<br />

at contractor's expenses, so he may stop the work together until he is<br />

satisfied and also impose a fine upon the contractors. The rate<br />

excavation includes pumping out any quantities of water as<br />

mentioned above by using any number of pumps and for any length<br />

and time singly or in combination. Nothing extra, whatsoever, will<br />

be paid on this account during the execution of the whole work.<br />

19.0 KEEP EXCAVATION CLEAR OF WATER<br />

a) Where ground water is encountered or anticipated, the contractor<br />

shall provide sufficient pumps to handle the ingress of water and<br />

must provide and maintain in working order stand by pumping units<br />

to be available and employed in the event of mechanical failure.<br />

The contractor must also arrange for night and day manning and<br />

operating of the pumps wherever necessary to ensure that at all<br />

times and weather the work may proceed.<br />

b) The contractors shall not allow any accumulation of water either<br />

from the discharge of their dewatering pumps or their water<br />

connection on the site of their work. If an accumulation is<br />

unavoidable, it shall be treated with insecticides to the satisfaction of<br />

the Engineer. In case of failures to do this on the part of the<br />

contractors, such accumulation shall be treated by <strong>CIDCO</strong> at the<br />

cost of contractors.