<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 256<br />

3.9 DIVERSIONS:<br />

If diversions are necessary for the traffic they shall be provided and<br />

maintained as specified under specification No. BR. 1 of Red Book.<br />

3.10 DISPOSAL OF EXCAVATED MATERIALS:<br />

All the excavated materials shall be the property of <strong>CIDCO</strong>, unless<br />

specifically mentioned otherwise. When the useful excavated<br />

materials is to be used in embankment within a lead of 50 m. (about<br />

164’) it shall be directly deposited at the required location in 15 cm.<br />

to 20 cm. (about 6” to 8”) layers, the charge for watering and<br />

compacting such materials being paid under a separate item. No<br />

handling or conveyance charges shall be paid if the material is<br />

temporarily deposited elsewhere and subsequently conveyed to the<br />

site of deposition. The sequence of operations should be arranged<br />

properly. Useful excavated materials to be used in embankment<br />

beyond 50 m. (about 164’) may be conveyed directly to the site of<br />

use and laid in layers or first deposited in heaps and conveyed and<br />

laid in layers subsequently the conveyance and the charges for the<br />

watering and compaction shall be paid for under a separate item.<br />

Materials required for four times other than bank shall be arranged<br />

in neat stacked at convenient places within a load of 50 m. (about<br />

164’) without interfering with the drainage in any way. If no <strong>CIDCO</strong><br />

land is available but the excavated useful stuff is to be stacked<br />

temporarily before use under the same agreement the contractor<br />

shall make his own arrangement s for the stacking of his materials<br />

temporarily on private lands by paying rents etc. without claiming<br />

any compensation. Surplus cost to uniformly widen embankment to