<strong>CIDCO</strong> OF MAHARASHTRA LTD<br />

C.A.No.01/<strong>CIDCO</strong>/SE(KHR)/EE(KHR-I)/2010–11 Pg. No. 458<br />

11.0 UNAUTHORISED EXCESS EXCAVATION<br />

Where excavation are made in excess of the limits delineated on the<br />

drawings, either by error or by accident, the voids so formed shall be<br />

filled in with lime concrete or rubble masonry or otherwise at the<br />

discretion and to the satisfaction of the Engineer and at the expense<br />

of the contractors.<br />

12.0 FENCING/LIGHTING AND WATCHING<br />

The contractor shall make all proper provisions for protecting the<br />

work be fences and by watching and lighting at night, or otherwise<br />

as may be directed by the Engineer. The posts of fencing shall be<br />

timber securely fixed in the ground not more than 3 M. apart, and<br />

they shall not be less than 75 mm in diametre or less than 1.2 M.<br />

above the surface of the ground. There shall be two rails, one near<br />

the top of the posts and the other about 450 mm above the surface<br />

of the ground and each shall be from 50 mm to 70 mm in diametre<br />

and sufficiently long to run from post to post, to which they shall be<br />

bound with strong rope. The method of projecting rails beyond the<br />

posts and tying them together where they meet will not be allowed<br />

on any account. All along the edges of the excavated trenches a<br />

bank of earth about 1.20 M. high shall be formed where required by<br />

the Engineer for further protection. Proper provisions shall be made<br />

for lighting at night and watchman shall be kept to see that this is<br />

properly done. In the event of the contractors not fully complying<br />

with the provisions of these clause, the Engineer may, with or without<br />

notice to the contractors, put up a fence or improve the fence<br />

already put up or provide or improve the lighting or adopt such<br />

measures as he may deem necessary and all the cost of such<br />

procedure as may be adopted by the Engineer, shall be borne by the<br />

contractors.