Guide Specification<br />

N. NESC National Electrical Safety Code<br />

O. NFPA National Fire Protection Association<br />

P. OSHA Occupational Safety <strong>and</strong> Health Administration<br />

Q. TIA Telecommunications Industry Association<br />

R. TR Telecommunications Room<br />

S. TWC Tenant Wiring Closet<br />

T. UFBC Uniform Fire Prevention <strong>and</strong> Building Code<br />

U. UL Underwriter’s Laboratories, Inc.<br />

1.3 SUBMITTALS<br />

A. Comply with all LAWA submittal procedures given in other Sections. The following is in<br />

addition to or complementary to any requirements given elsewhere.<br />

B. Submit a detailed bill-of-materials listing all manufacturers, part numbers, <strong>and</strong> quantities that<br />

the Bidder proposes to use in this project.<br />

C. Submit all proposed labeling materials <strong>and</strong> nomenclature for approval.<br />

D. Coordination Drawings:<br />

1. Indicate locations where space is limited for installation <strong>and</strong> access.<br />

2. Submit floor plans, elevations, <strong>and</strong> details indicating major equipment <strong>and</strong> end device<br />

locations of equipment to be provided by this contractor to interface to existing systems.<br />

E. Project Record Documents required include:<br />

1. Marked-up copies of Contract Drawings<br />

2. Marked-up copies of Shop Drawings<br />

3. Newly prepared Drawings<br />

4. Marked-up copies of Specifications, Addenda <strong>and</strong> Change Orders<br />

5. Marked-up Project Data submittals<br />

6. Record Samples<br />

7. Field records for variable <strong>and</strong> concealed conditions<br />

8. Record information on Work that is recorded only schematically<br />

9. As-built drawings<br />

10. Record drawings<br />

11. Electronic as-built <strong>and</strong> LAWA LUSAD requirements<br />

COMMUNICATION SYSTEMS INTERFACES (LEGACY SYSTEMS)<br />

27 13 33 - 2<br />

Communication Systems