Guide Specification<br />

J. Install from grounding bus of serving panel to ground bus of served panel, grounding<br />

screw of receptacles, lighting fixture housing, light switch outlet boxes or metal<br />

enclosures of service equipment. Ground conduits by means of grounding bushings on<br />

terminations at panelboards with installed number 12 conductor to grounding bus.<br />

K. Permanently attach equipment <strong>and</strong> grounding conductors prior to energizing equipment.<br />

L. The Ufer ground grounding electrode shall consist of a 50-foot length of bare #4/0<br />

copper wire extended its full length below ground level <strong>and</strong> embedded along the bottom<br />

of the concrete foundation footing which is in direct contact with the foundation earth<br />

<strong>and</strong> supported in such a manner that it cannot be less than 3 inches from the bottom or<br />

side of the concrete when the foundation concrete is poured.<br />

A loop at the approximate center of this grounding electrode shall be brought out at the<br />

top of the foundation <strong>and</strong> a #4/0 copper ground conductor shall connect the ground<br />

electrode to the main ground electrode bus in the equipment room. The conductor shall<br />

be connected to the ground electrode by exothermic welding.<br />

3.4 FIELD QUALITY CONTROL<br />

A. Inspect <strong>and</strong> test in accordance with NETA ATS, except Section 4.<br />

B. Grounding <strong>and</strong> Bonding: Perform inspections <strong>and</strong> tests listed in NETA ATS, Section<br />

7.13.<br />

C. Perform ground resistance testing in accordance with IEEE 142.<br />

D. Perform leakage current tests in accordance with NFPA 99.<br />

E. Perform continuity testing in accordance with IEEE 142.<br />

F. When improper grounding is found on receptacles, check receptacles in entire project<br />

<strong>and</strong> correct.<br />

G. Perform retest.<br />

END OF SECTION 26 05 27<br />

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS<br />

26 05 27 - 5 Electrical Systems