conforming work <strong>and</strong> shall be submitted to the Engineer for review <strong>and</strong> approval prior<br />

to any corrective action taking place. If the Contractor fails to remove, replace, or<br />

correct any non-conforming Work or materials within seventy-two (72) hours of<br />

discovery, the Engineer may cause such Work or materials to be removed <strong>and</strong><br />

replaced. Such removal <strong>and</strong> replacement shall be at the sole expense of the<br />

Contractor <strong>and</strong> all such cost shall be deducted from any moneys that are due or may<br />

become due to the Contractor. Otherwise the Contractor shall pay LAWA if there<br />

remains an insufficient amount or no amount to be paid by LAWA to the Contractor.<br />

C. Any delays or impacts arising on the Work as a result of construction or delivery of<br />

non-conforming Work or materials shall be at the Contractor's sole expense.<br />

D. Failure of the Inspector or the Engineer to notify the Contractor of any nonconforming<br />

Work shall not constitute acceptance of any non-conforming Work. The<br />

Contractor's obligation to remove, replace or correct any non-conforming Work,<br />

whenever discovered, shall continue to the end of the warranty period specified in<br />

the Contract Documents. LAWA reserves <strong>and</strong> retains all rights <strong>and</strong> remedies against<br />

the Contractor <strong>and</strong> their Surety for correction of any <strong>and</strong> all latent defects discovered<br />

after the warranty period.<br />

E. If the Contractor shall join Work with any Work in place, <strong>and</strong> if such joint is not made<br />

in a skillful manner, then such joint or Work shall be deemed <strong>and</strong> construed to be<br />

faulty workmanship <strong>and</strong> such materials shall be deemed <strong>and</strong> construed to be<br />

defective materials.<br />

F. In case of a dispute between the Contractor <strong>and</strong> the Inspector, the latter is<br />

authorized to reject materials or suspend the Work until any questions at issue can<br />

be referred to <strong>and</strong> decided by the Engineer<br />

MATERIALS AND WORKMANSHIP<br />

A. Workers <strong>and</strong> installers shall be skilled, trained <strong>and</strong> experienced in the necessary<br />

crafts <strong>and</strong> shall be completely familiar with the specific requirements <strong>and</strong> methods<br />

needed for proper performance <strong>and</strong> completion of the Work.<br />

B. Fabricators shall be licensed by the City of <strong>Los</strong> <strong>Angeles</strong>. All structural welding shall<br />

be performed by welders certified <strong>and</strong> licensed by the City of <strong>Los</strong> <strong>Angeles</strong>,<br />

Department of Building <strong>and</strong> Safety.<br />

C. No product containing asbestos shall be used for any purpose. When removing<br />

asbestos products, the Contractor shall comply with the requirements of Title 8,<br />

CCR, General Industry Safety Orders <strong>and</strong> <strong>Construction</strong> Safety Orders.<br />

D. All references to specifications of national organizations <strong>and</strong> trade associations<br />

related to building industry such as, but not limited to, American Society for Testing<br />

<strong>and</strong> Materials, American Institute of Steel <strong>Construction</strong>, American Concrete Institute,<br />

Prestressed Concrete Institute, Post-Tensioning Institute, <strong>and</strong> the National Board of<br />

Fire Underwriters refer to the latest revision of such specifications except as<br />

otherwise noted at time of bid opening.<br />

<strong>Design</strong> <strong>and</strong> <strong>Construction</strong> H<strong>and</strong>book<br />

74 of 84<br />

H<strong>and</strong>book (Version 3) 01.15.11